Elwha dams electrical turbines turned off for good
By Paul Gottlieb
Peninsula Daily News
Print This |
Email This
Recent Headlines
Car plows into west Port Angeles grocery -- 5/16/12 -12:47 PM
Sequim ‘dilemma’: Fixing streets to cost $8.5 million over 5 years -- 5/15/12 -05:42 PM
Seven recognized in Jefferson County with Heart of Service Awards -- 5/15/12 -05:17 PM
Protesters march to Sequim council meeting to seek rescheduling of biomass forum -- 5/15/12 -05:42 PM
More candidates file in Clallam County, state -- 5/15/12 -05:35 PM
“Let bygones be bygones,” Elwha Dam power plant supervisor Kevin Yancy said.
“It’s the end of an era on the Elwha,” Yancy added, standing in a power plant control room packed with reporters shortly after he separated the Elwha Dam’s three-generator transmission line from the Bonneville Power Administration grid.
The Glines Canyon Dam’s single 18-foot-diameter turbine was shut down about an hour earlier, at 8:20 a.m.
“K. Yancy, on site to shut down G. Canyon power plant,” Yancy wrote in the dam’s maintenance log.
“Good by Glines.”
Barnard Construction Co. of Bozeman, Mont., will begin tearing down the dams Sept. 17 in a $26.9 million contract with the National Park Service.
The Elwha watershed is in Olympic National Park, as is Glines Canyon Dam.
The dams are being torn down as part of the $327 million Elwha River Restoration Act.
________
Senior Staff Writer Paul Gottlieb can be reached at 360-417-3536 or at paul.gottlieb@peninsuladailynews.com.
Last modified: June 01. 2011 11:23AM



To report a comment, email moderator@peninsuladailynews.com and refer to the article and offending comment, or click here: REPORT ABUSE.
Peninsuladailynews.com comments are subject to the Peninsuladailynews.com User Policy.