Cost rises for Port of Port Angeles stormwater treatment facility construction

PORT ANGELES — The Port of Port Angeles’ Marine Terminal Stormwater Treatment facility, originally budgeted for $2.05 million, will cost $2.36 million to build and $2.73 million overall.

Port commissioners approved a construction bid Tuesday for the project north of Marine Drive on the industrial waterfront.

Commissioners Connie Beauvais, Colleen McAleer and Steve Burke unanimously approved the $2.36 million construction bid for the taxing district’s largest capital project for 2018 to low bidder Interwest Construction Inc. of Burlington.

Other project costs including $150,000 for design, $120,000 for contingency and $45,000 estimated for construction administration pushed the project cost to $2.73 million, boosting the price tag to $680,000 over budget, or 30 percent more than was allocated in the 2018 capital budget.

The $680,000 will be drawn from the port’s capital reserves, reducing the $7.5 million balance by 9 percent.

Beauvais, McAleer and Burke were unavailable for comment Tuesday afternoon.

The treatment project must be built by Sept. 30 under an administrative order from the state Department of Ecology that the port deal with untreated stormwater from the port’s industrialized shoreline are that flows freely into Port Angeles Harbor.

Construction will begin by mid- to late June, with little impact on the public expected.

A low wall and three large concrete boxes up to 5 feet tall will be installed near the port’s Terminal 3 dock off the Boat Haven parking lot.

When it went out to bid in April, the project was estimated to cost $2.05 million for construction and $200,000 for design, exceeding the budget — not including $171,000 in sales taxes — by $150,000.

Engineering Director Chris Hartman told Peninsula Daily News on April 13 that the increased cost was due to design work that made the project more “site specific,” to avoid a chemical treatment process and to expand the area planned for paving.

The cost is now $2.73 million because of the contingency amount that was added and bids came in higher than anticipated, Hartman said.

“We’ve seen construction costs escalate,” he said after the meeting Tuesday.

“That’s a portion of it, and the other part of is we budgeted the project prior to final design.

“Costs can escalate as designs get tweaked and finalized.”

Kennedy/Jenks Consultants Inc., which has an office in Seattle, was the engineering firm that did the design and construction estimate for the Marine Terminal Stormwater Treatment Project.

The project will consist of biofiltration garden and three concrete box-like cells up to 5 feet tall near the Terminal 3 dock.

It will process up to 5.5 million gallons of polluted runoff before it pours through a new outfall into the harbor.

A pump installed in the current outfall will move stormwater to the new treatment facility and will be used solely for high-rain events.

The port agreed with Ecology to install the new system after exceeding permitted levels for 12 months.

Pollutants including copper and zinc, which are toxic to salmonids, at higher levels than allowed in the permit.

Reid Middleton of Everett was the engineering firm that did the design and construction estimate for an estimated $1.63 million vessel wash-down facility that is the port’s second largest capital project for 2018.

The original construction cost estimate was $2.46 million, higher than the budgeted amount, for the facility, which will serve Westport Shipyard on Marine Drive, Platypus Marine on North Cedar and new tenants in the Marine Trades Industrial Park.

Cost reductions included transporting wash-water effluent to a nearby port treatment site instead of building a treatment facility and the option of building a 93-foot concrete wash pad that would be slightly more than half the size of a wash pad that could have more easily accommodated Westport’s 164-foot yachts.

Port officials are hoping the wash-down facility will spark tenant interest in the industrial park.

It is expected to be completed by Oct. 31. Port officials have said the wash-down is vital to development of the 18-acre site, which went through $7 million of environmental cleanup following decades as the location of a plywood mill.

________

Senior Staff Writer Paul Gottlieb can be reached at 360-452-2345, ext. 55650, or at pgottlieb@peninsuladailynews.com.

More in News

A mud slide brought trees down onto power lines on Marine Drive just each of the intersection with Hill Street on Monday. City of Port Angeles crews responded and restored power quickly. (Dave Logan/for Peninsula Daily News)
Downed trees

A mud slide brought trees down onto power lines on Marine Drive… Continue reading

Photographers John Gussman, left, and Becky Stinnett contributed their work to Clallam Transit System’s four wrapped buses that feature wildlife and landscapes on the Olympic Peninsula. The project was created to promote tourism and celebrate the beauty of the area. (Paula Hunt/Peninsula Daily News)
Iconic Peninsula images wrap Clallam Transit buses

Photographers’ scenes encompass community pride

Housing identified as a top priority

Childcare infrastructure another Clallam concern

Giant ornaments will be lit during the Festival of Trees opening ceremony, scheduled for 5 p.m. Wednesday. (Olympic Medical Center Foundation)
Opening ceremony set for Festival of Trees

‘White Christmas’ to be performed in English, S’Klallam

Olympia oyster project receives more funding

Discovery Bay substrate to receive more shells

Code Enforcement Officer Derek Miller, left, watches Detective Trevor Dropp operate a DJI Matrice 30T drone  outside the Port Angeles Police Department. (Port Angeles Police Department)
Drones serve as multi-purpose tools for law enforcement

Agencies use equipment for many tasks, including search and rescue

Sequim Heritage House was built from 1922-24 by Angus Hay, former owner of the Sequim Press, and the home has had five owners in its 100 years of existence. (Matthew Nash/Olympic Peninsula News Group)
Sequim’s Heritage House celebrates centennial

Owner hosts open house with family, friends

Haller Foundation awards $350K in grants

More than 50 groups recently received funding from a… Continue reading

Operations scheduled at Bentinck range this week

The land-based demolition range at Bentinck Island will be… Continue reading

Weekly flight operations scheduled

There will be field carrier landing practice operations for aircraft… Continue reading

Jefferson County lodging tax committee to meet

The Jefferson County Lodging Tax Advisory Committee will discuss… Continue reading

Restrictions lifted on left-turns near Hood Canal bridge

The state Department of Transportation lifted left-turn restrictions from… Continue reading