Closures for fish passages shortened

DOT says Tumwater Creek project down to 80 days

PORT ANGELES — A project to install a fish passage at Tumwater Creek in Port Angeles is now expected to close U.S. Highway 101 for 80 days, down from the nine-month timeline previously projected by the state Department of Transportation.

“(Kiewit Infrastructure West) is ambitious and they have committed to accomplishing the bridge constriction in 80 days,” said Piper Petit, a project engineer with DOT. “The intention is still to have the road back open before Memorial Day.”

Speaking to a meeting of the Port Angeles Business Association on Tuesday, Petit said construction on the Tumwater project is scheduled to begin in January 2025. The project will close down a portion of Highway 101 through Port Angeles, redirecting traffic through the downtown area.

ADVERTISEMENT
0 seconds of 0 secondsVolume 0%
Press shift question mark to access a list of keyboard shortcuts
00:00
00:00
00:00
 

Eastbound traffic on Highway 101 will be redirected off the roadway at the Tumwater Truck Route and westbound traffic will be stopped just past Lauridsen Boulevard, Petit said.

The Tumwater project is just one of dozens of fish passage projects on the North Olympic Peninsula currently being worked on by DOT due to a 2013 federal injunction that found the state has a duty to remove barriers to fish migration.

Under the injunction, the state has until 2030 to remove 90 percent of blocked habitat, and as of 2023, DOT had corrected more than 115 culverts throughout western Washington.

Several fish barrier projects are scheduled for this summer on Highway 101 south of Forks, and will limit traffic to one lane to be controlled by a temporary signal in each direction.

Contractor crews began construction of a temporary bridge on Highway 101 at the Clallam and Jefferson county line south of Forks this week.

Once the temporary bridge is completed, traffic will be diverted onto it to allow for the replacement of an outdated culvert on May Creek with a 175-foot bridge. The bridge is expected to be completed in fall 2026.

Replacement projects also are planned for Lees and Ennis creeks, and Petit said the winning contracts for those projects have said they can limit road closures to 20 days.

A series of fish passage projects are scheduled for state Highway 112, which will require detours to other routes. While the department has made good progress on fish passage projects on the North Olympic Peninsula, Petit said construction work will likely continue in the region up to 2030 and maybe even later, based on the department’s work schedule.

Bridges

Work on replacing the Elwha Bridge on Highway 101 west of Port Angeles is continuing, and all three spans of the bridge have been installed, according to Brian Whitehouse, assistant construction engineer with DOT. Concrete will be poured in the coming weeks.

The old bridge remains open to traffic but will be closed for nine days in mid-June as ties to the ends of the bridge are constructed. Traffic will be detoured onto Highway 112, Whitehouse said.

The Hood Canal Bridge also is scheduled for additional maintenance this summer, some involving overnight closures — but no weekend closures — between May and June. Whitehouse said DOT is currently working with the contractor to develop an hourly schedule.

Work on the bridge last summer was initially scheduled to close the bridge for several weekends, prompting concerns from local communities about the impacts on the local economy, particularly the tourism industry. DOT eventually reworked the schedule so that work and closures happened overnight, and Whitehouse said the department is following the same model for this year’s work.

Roundabouts

Construction on two roundabouts west of the Hood Canal Bridge are set to begin this year and will require traffic to be detoured off state Highway 104. Roundabouts are being installed on Highway 104 at the intersection with Shine and Paradise Bay roads and at the intersection with state Highway 19.

Those projects are expected to close a portion of State Route 19 for 21 days between May 1 and June 15, Whitehouse said.

DOT is looking at installing roundabouts on Highway 101 between Port Angeles and Sequim, Petit said, although those projects are still in the planning phases.

“It’s not much more than an idea at the moment,” Petit said of the roundabouts, and noted there will be opportunities for public feedback before those projects move forward.

Information and updates on DOT’s projects are available at the department’s website, wsdot.wa.gov, and real-time updates on closures and road conditions can be found on DOT’s social media.

________

Reporter Peter Segall can be reached at peter.segall@peninsuladailynews.com.

More in News

Gary Norris, front, takes a photo of the Rayonier No. 4 as Leo Frymire looks on during a tour of the engine on Sunday at Lauridsen Boulevard and Chase Street in Port Angeles. They attended a fundraiser for Restore the 4!, a local group leading the effort to restore the geared locomotive built in 1924 by Willamette Iron and Steel in Portland, Ore. The North Olympic History Center, which helped organize the event, donated $1,000 toward the cause. More than 100 people attended a presentation by Steve Hauff, a local historian and expert on Willamette logging locomotives, at the Port Angeles Main Library beforehand. (Keith Thorpe/Peninsula Daily News)
Locomotive fundraiser

Gary Norris, front, takes a photo of the Rayonier No. 4 as… Continue reading

Court denies recall petition

Sequim man files motion to reconsider

Former Washington Supreme Court Justice Susan Owens dies

Judge spent 19 years on Clallam County District Court bench

Boatbuilding school names executive director

Local candidate chosen from national pool

Road improvement project set at Lincoln Park

The city of Port Angeles will perform road improvements… Continue reading

Matthew Nash/Olympic Peninsula News Group
Sisters Jasmine Kirchan, left, and Shawnta Henry and their mom Nicole Kirchan all work at the Sequim Boys & Girls Club. After work on Feb. 26, they all helped save the life of a man in front of Walmart.
Sequim woman uses CPR training to save man outside Walmart

She credits training to Boys Girls Club, fire district

The 104-lot Bell Creek Major Subdivision and 24-lot Bella Vista Estates recently were approved by Sequim Hearing Examiner Peregrin Sorter. (Matthew Nash/Olympic Peninsula News Group)
Hearing examiner approves 2 projects

Developments could add 128 homes in Sequim

No flight operations scheduled this week

There will be no field carrier landing practice operations for… Continue reading

2024 timber revenue shows Jefferson below average, Clallam on par

DNR timber delay could impact 2025 timber revenue

Forks council looks to fill vacant seat

The Forks City Council is accepting applications to fill a… Continue reading

Charter Review town hall set

The Clallam County Charter Review Commission will conduct a… Continue reading