Elwha River claims section of road with massive washout; campground buried in silt, debris

OLYMPIC NATIONAL PARK — The Elwha River flexed its new muscles during the most recent round of storms and severely damaged Olympic Hot Springs Road and effectively buried a campground in silt.

The river rose to 23.19 feet on Nov. 17 during a heavy rainstorm that produced 5.6 inches of rain on that date in the Elwha watershed, as measured at the Buckinghorse Snotel site.

When the water receded, Olympic National Park officials discovered the water had washed out a 60-foot-long section of Olympic Hot Springs Road, and much of Elwha Campground had nearly disappeared under more than a foot of silt and debris, Barb Maynes, spokeswoman for the park, had said over the weekend.

“The washout was caused by a flooded side channel,” Maynes said Sunday.

Flood stage for the Elwha River is 20 feet, “moderate flood stage” is 21.5 feet and “major flood stage” is 23 feet, as measured at the McDonald Bridge south of the campground.

It is the highest the river has reached since the Elwha and Glines Canyon dams were removed, and the seventh highest crest recorded, according to National Weather Service records dating back to the late 1800s.

The highest crest recorded at the site was 24.65 feet in 2007, Weather Service records showed.

“Other areas in the [Elwha] valley have seen damage — extensive damage,” Maynes said.

“Park staff is still assessing the damages,” she said.

Maynes said there is no established timeline yet for repairs or reopening damaged Elwha roads and campgrounds.

Elwha River valley attractions and roads have been opened and closed several times over the past few years due to dam removal, washouts and floods.

Olympic Hot Springs Road south of Altair Campground was closed for three years while crews removed the Glines Canyon Dam.

It reopened in November 2014 and provided access to the west Glines Canyon overlook, a remnant of the former dam, and to the Olympic Hot Springs Trail.

Altair Campground has been closed since December 2014 due to road and campsite damage during floods.

A storm in January caused a slide on the nearby Whiskey Bend Road that destroyed 50 feet of roadway.

Park crews completed repairs at the slide, located about 4 miles from the road’s intersection with Olympic Hot Springs Road, and it was reopened Oct. 30.

The road provides access to the east Glines Canyon overlook.

A February flood resulted in damage to the Olympic Hot Springs Road near the Madison Creek Falls trailhead, where the road was closed for several weeks in September for repairs.

The road repair, called “rootwad revetments,” used natural materials to reduce erosion by burying downed trees with their roots exposed to the stream, with boulders, rock and gravel securing the tree trunks under the new roadbed.

September’s repairs to both roads survived the most recent storm and flood, Maynes said.

Elsewhere in the park, Queets, North Shore Quinault, Graves Creek and North Fork roads remained closed Sunday due to storm damage.

As of Sunday, the Kalaloch, Mora, Ozette, Hoh, Lake Crescent and Staircase areas were accessible.

The Hurricane Ridge Road and the Sol Duc Road remain closed Sunday due to snow.

The park reported 21 inches of snow at the ridge.

Snow plow operations on Hurricane Ridge Road are expected to begin Friday to open the popular destination for the winter season.

The road is scheduled to be open during daylight hours Fridays through Sundays and Monday holidays, weather permitting.

All vehicles must carry tire chains when traveling to Hurricane Ridge during winter.

Hurricane Ridge Ski and Snowboard Area has not yet scheduled an opening date.

________

Reporter Arwyn Rice can be reached at 360-452-2345, ext. 5070, or at arice@peninsuladailynews.com.

Reporter James Casey can be reached at 360-452-2345, ext. 5074, or at jcasey@peninsuladailynews.com

More in News

The section of state Highway 20 leading into downtown Port Townsend is aglow with autumn color from the early morning sunshine reflecting off the poplar trees that line the roadway. (Steve Mullensky/for Peninsula Daily News)
Fall colors

The section of state Highway 20 leading into downtown Port Townsend is… Continue reading

Clallam Transit to hire security agency for downtown Port Angeles location

Two-year contract aims to curb recurring unlawful activities

Jefferson County letter addresses funding obligation

Board says prosecuting attorneys will try fewer cases

Planning workshop to cover Port Townsend comprehensive plan

The Port Townsend City Council, Port Townsend Planning Commission… Continue reading

Access to Paradise Bay road to close for three weeks

Access from state Highway 104 to Paradise Bay Road… Continue reading

Clallam County commissioners to host budget presentations

The Clallam County commissioners will present the county’s proposed… Continue reading

Public comment open on proposed PNNL aquatic research

The U.S. Department of Energy will host public meetings at… Continue reading

‘Your voice’ program aims to increase civil engagement

Owl 360, Antioch University and the Jefferson County Clemente… Continue reading

Five rescued from tug off coast of La Push

Concrete barge waiting to be towed to shore

Lt. Cmdr. Lyndsay P. Evans.
Two Navy crew members who went missing after crash identified

Two U.S. Navy crew members who were missing after their aircraft crashed… Continue reading

Sales of fireworks will be prohibited in Sequim city limits effective late October 2025 after Sequim city council members voted to restrict the sale. The decision comes seven years after former city council members voted to ban the discharge of fireworks in city limits. (Matthew Nash/Olympic Peninsula News Group file)
Sequim to ban fireworks sales

Ordinance to go into effect next fall

The West Sequim Bay Corridor Project, including a lift station at Forrest Road, is the largest project for the city of Sequim in 2025. Nick Dostie, Sequim’s city engineer and deputy director of public works, previously said the city plans to go to bid in the second or third quarter of 2025, with construction possibly starting in the first quarter of 2026, and pipeline and lift station construction complete in the third or fourth quarter of 2028. (Matthew Nash/Olympic Peninsula News Group)
Sequim’s $58M budget largest in history

Utility rate increase continues three-year plan