Explosion brings down more of Glines Canyon Dam [ *** GALLERY *** ]

OLYMPIC NATIONAL PARK — An explosion took down about an additional 6 feet of Glines Canyon Dam last week, and at least one more explosion is expected next month.

Barnard Construction Company Inc. crews blew up a portion of the upper dam on the Elwha River on Thursday.

“We took out some of the concrete from the dam that we couldn’t get to with the barge on the far right-hand side [looking downstream],” said Brian Krohmer, project manager.

“The shoreline is too shallow for the barge, so we had to drill and blast it,” he said.

Glines Canyon Dam is now about 42 feet shorter than its original 210-foot height.

Barnard, a Bozeman, Mont.-based company contracted by Olympic National Park to remove both Glines Canyon Dam and the lower Elwha Dam, drilled holes for the explosives during snowstorms the week of Jan. 15.

Crews used a “man basket” to lower themselves to that section of the dam, Krohmer said.

At least one more explosion will be needed later on that side of the Glines Canyon Dam, Krohmer said.

Before that happens, crews will chisel another 3 feet or so off the top of the dam by midweek and then wait through a 14-day hold period designed to give the river time to erode the sediment in the Lake Mills delta.

Underwater pillars

During the hold period, Barnard crews will install two underwater pillars called “spud piles” on the front corners of the barge.

The piles will brace the barge against the face of the dam.

After the two-week hold period, “we’ll have at least one more blast on that side” of Glines Canyon Dam, Krohmer said, which will remove another 6- to 8-foot section.

“There’s so much rebar in the concrete next to the embankment that it’s difficult to drill,” he added.

“There are still a lot of unknowns there,” Krohmer said.

“There’s a lot of work left to do.”

The dam is expected to be completely demolished in early 2014.

“Glines is obviously going to take longer to complete than the Elwha Dam,” Krohmer said.

The Elwha Dam is expected to be completely removed by early 2013.

Work is much farther along there.

Some 44 feet remains to be removed from the lower dam, which was originally 108 feet tall, so it won’t be long before the visible part of the dam is taken down to the riverbed.

“What you can’t see is the work on the powerhouse,” Krohmer said.

“We’re still removing the substructure of that,” and that work should be finished by midweek, Krohmer said.

The river was diverted to the left channel late last week and will remain there for three to five weeks while crews finish removing the gravity dam.

Then, crews will begin moving some 67,000 cubic yards of dirt and rock that were fill material just upstream of the dam.

The material will be placed on the slope where the powerhouse and penstocks, the large metal pipes that led from the dam to the powerhouse, once stood.

Barnard Construction crews began in September chipping away at the two dams, built without fish ladders nearly a century ago, as part of a $325 million federal project to restore the river’s once-famous salmon runs.

The Elwha Dam was built in 1913 five miles from the mouth of the river, forming the now-disappeared Lake Aldwell, and the Glines Canyon Dam, which formed Lake Mills 14 miles upriver, followed in 1927.

More in News

John Gatchet of Gardiner, left, and Mike Tabak of Vancouver, B.C., use their high-powered scopes to try to spot an Arctic loon. The recent Audubon Christmas Bird Count reported the sighting of the bird locally so these bird enthusiasts went to the base of Ediz Hook in search of the loon on Sunday afternoon. (Dave Logan/for Peninsula Daily News)
Bird watchers

John Gatchet of Gardiner, left, and Mike Tabak of Vancouver, B.C., use… Continue reading

Forks schools to ask for levy

Measure on Feb. 11 special election ballot

Jefferson County commissioners name Pernsteiner acting sheriff

Jefferson Democrats to nominate three interim candidates

State commission fines fire commissioner

PDC says Kraft owes more than $4,600

Marine Center receives $15 million

Funding comes from Inflation Reduction Act

Port Townsend creates new department to oversee creative district

Melody Sky Weaver appointed director of Community Service Department

Orca that carried dead calf for weeks is mourning again

The mother orca nudges her dead calf with her snout, draping it… Continue reading

Weekly flight operations scheduled

There will be field carrier landing practice operations for aircraft… Continue reading

Will Barrett of Port Townsend and his cairn terrier Harris brave the cold and wet weather on Friday to walk around the Marine Science Center pier at Fort Worden State Park. (Steve Mullensky/for Peninsula Daily News)
Rainy walk

Will Barrett of Port Townsend and his cairn terrier Harris brave the… Continue reading

Kate Dean.
Kate Dean reflects on Jefferson County career

Will work for state office of Public Lands

The Hub, a place to form community connections and incubate ideas, hosts a Night Market on the third Friday of every month. CEO Roxanne Greeson invited people to drop by for one of their events, or stop by between 10 a.m. and 8 p.m. Tuesday through Saturday, to see what they think of the space. (Roxanne Greeson)
The Hub aims to incubate ideas, grow community

PA business hosts spaces for artists, storefront to sell creations

Food resources are available across Peninsula

Officials say demand continues to rise over previous years