Hitch in Hood Canal Bridge project, state Transportation says; west-half hydraulic system worries continue

  • State Department of Transportation news release
  • Thursday, February 25, 2010 1:42pm
  • News

State Department of Transportation news release

SHINE – WSDOT is delaying the completion of the SR 104 Hood Canal Bridge project after functional testing of the bridge revealed poor performance of the west-half lift span hydraulic system.

“While conducting functional testing of the hydraulic systems we were able to identify this issue before it became an operational problem,” said Kevin Dayton, WSDOT region administrator. “Unfortunately, this testing phase has also caused unplanned and unexpected delays for travelers. We appreciate the community’s continued patience as we work to solve the draw span problem.”

Engineers are trying to determine why the rear hydraulic lifts of all three structures that make up the west-half draw span are operating slower than the front lifts. The systems are producing different pressures, which are causing the lift spans to operate at different speeds. Final testing work by contractor Kiewit-General was scheduled to wrap up by the end of February.

The Hood Canal Bridge’s west half was widened in 2006 with retrofit work on the lift systems occurring in 2009. The entire east half was replaced in May-June 2009 and continues to operate and open for marine vessels while the west-half retrofit continues.

Until the cause of the hydraulic issue is identified, most of the draw span testing – which requires closing the bridge to vehicle traffic – will be suspended although drivers may experience sporadic, daytime diagnostic test openings of up to 10 minutes, and continued weeknight test openings of up to 90 minutes between 10 p.m. and 4 a.m. WSDOT will provide at least 24 hours notice prior to nighttime closures. Whenever possible and to reduce the impact on motorists, these openings will be timed to occur during marine vessel openings.

Once the hydraulic issue is resolved, WSDOT estimates that functional testing will take about six nights of up to 90-minute closures between 10 p.m. and 4 a.m. to complete. West-half functional testing is approximately 50 percent finished, and will be followed by about three nights of tests of both the east and west draw spans. When functional testing and operational retrofitting work is complete, construction work on the bridge will conclude.

In May, crews from WSDOT’s Bridge Preservation Office will conduct federally-required annual inspections on the Hood Canal Bridge. The inspections, which include a total review of all systems, are standard for all moveable bridges in Washington and will require approximately three weeks of short-duration daytime and nighttime openings.

For more information, visit www.HoodCanalBridge.com

More in News

Claus Janssen, left, and Glenn Jansen, members of Port Townsend Urban Sketchers, sketch the fountain at Manresa Castle in Port Townsend. The group chooses a different location every month and meets at 10 a.m. and sketches until noon. (Steve Mullensky/for Peninsula Daily News)
Urban sketching

Claus Janssen, left, and Glenn Jansen, members of Port Townsend Urban Sketchers,… Continue reading

Chimacum location selected for a pool

Public facilities district could change site

Port Angeles school board agrees on salary for next superintendent

Directors say $220K will help them in competitive search

Nellie Bridge.
Clallam County names second poet laureate

Two-year term set to begin in April

Pacific Northwest Ballet dancers Elle Macy, center, and Dylan Wald take their bows with pianist Paige Roberts Molloy at Sunday’s Winter Ballet Gala. Roberts Molloy played Beethoven’s Sonata in F minor, the “Appassionata,” as Macy and Wald danced across the Port Angeles High School Performing Arts Center stage. (Diane Urbani de la Paz/for Peninsula Daily News)
Taking a bow

Pacific Northwest Ballet dancers Elle Macy, center, and Dylan Wald take their… Continue reading

Kathy Downer, a Sequim City Council member, resigned on Jan. 13 to spend more time with family. She was elected to office in 2021 and reelected to a different position in 2023. (Matthew Nash/Olympic Peninsula News Group)
Interviews are set for Sequim opening

Special meeting Feb. 3 for council candidates

Kindergartener Zoey Griffin eats lunch with classmates in Amy Skogsberg’s class. For most of Greywolf Elementary’s history, students have eaten in their classrooms as the school was built without a dedicated cafeteria. A bond proposal includes building a cafeteria at the school, improving its parking lot and bus loop, and updating its air handler and heating units. (Matthew Nash/Olympic Peninsula News Group)
Sequim schools bond would include cafeteria at Greywolf Elementary

Transportation center also needs attention, staff say

Layla Forêt is the new market director for the Sequim Farmers and Artisans Market. She formerly served as marketing manager. (Sequim Farmers and Artisans Market)
Sequim Farmers and Artisans Market hires director

Forêt has worked in marketing for past decade

Weekly flight operations scheduled

There will be field carrier landing practice operations for aircraft… Continue reading

Commander R.J. Jameson, center, exits the change of command ceremony following his assumption of the role on Friday at the American Legion Hall in Port Townsend. (Elijah Sussman/Peninsula Daily News)
Naval Magazine Indian Island sees change in command

Cmdr. R.J. Jameson steps into role after duties across world

Allen Chen.
Physician officer goes back to roots

OMC’s new hire aims to build services

f
Readers give $111K in donations to Home Fund

Donations can be made for community grants this spring