Hitch in Hood Canal Bridge project, state Transportation says; west-half hydraulic system worries continue

  • State Department of Transportation news release
  • Thursday, February 25, 2010 1:42pm
  • News

State Department of Transportation news release

SHINE – WSDOT is delaying the completion of the SR 104 Hood Canal Bridge project after functional testing of the bridge revealed poor performance of the west-half lift span hydraulic system.

“While conducting functional testing of the hydraulic systems we were able to identify this issue before it became an operational problem,” said Kevin Dayton, WSDOT region administrator. “Unfortunately, this testing phase has also caused unplanned and unexpected delays for travelers. We appreciate the community’s continued patience as we work to solve the draw span problem.”

Engineers are trying to determine why the rear hydraulic lifts of all three structures that make up the west-half draw span are operating slower than the front lifts. The systems are producing different pressures, which are causing the lift spans to operate at different speeds. Final testing work by contractor Kiewit-General was scheduled to wrap up by the end of February.

The Hood Canal Bridge’s west half was widened in 2006 with retrofit work on the lift systems occurring in 2009. The entire east half was replaced in May-June 2009 and continues to operate and open for marine vessels while the west-half retrofit continues.

Until the cause of the hydraulic issue is identified, most of the draw span testing – which requires closing the bridge to vehicle traffic – will be suspended although drivers may experience sporadic, daytime diagnostic test openings of up to 10 minutes, and continued weeknight test openings of up to 90 minutes between 10 p.m. and 4 a.m. WSDOT will provide at least 24 hours notice prior to nighttime closures. Whenever possible and to reduce the impact on motorists, these openings will be timed to occur during marine vessel openings.

Once the hydraulic issue is resolved, WSDOT estimates that functional testing will take about six nights of up to 90-minute closures between 10 p.m. and 4 a.m. to complete. West-half functional testing is approximately 50 percent finished, and will be followed by about three nights of tests of both the east and west draw spans. When functional testing and operational retrofitting work is complete, construction work on the bridge will conclude.

In May, crews from WSDOT’s Bridge Preservation Office will conduct federally-required annual inspections on the Hood Canal Bridge. The inspections, which include a total review of all systems, are standard for all moveable bridges in Washington and will require approximately three weeks of short-duration daytime and nighttime openings.

For more information, visit www.HoodCanalBridge.com

More in News

Cities, counties approve tax hikes

State law allows annual 1 percent increase

Health officer: Respiratory illnesses low on Peninsula

Berry says cases are beginning to rise regionally

A puppy named Captain Kirk is getting ready for adoption by Welfare for Animals Guild after it was rescued near Kirk Road. An unsecured makeshift kennel fell out of a truck on U.S. Highway 101 last month and was struck by another vehicle. (Welfare for Animals Guild)
Puppy rescued from wreck to be adopted

A puppy named Captain Kirk is about to boldly go… Continue reading

Festival of Trees raises record $231,000

The 34th annual Festival of Trees, produced by the… Continue reading

Man flown to hospital after single-car collision

A 67-year-old man was flown to an Everett hospital after… Continue reading

Lost Mountain Station 36 at 40 Texas Valley Road recently sold to a neighbor after Clallam County Fire District 3 was unable to recruit volunteers to staff the station. Its proceeds will go toward future construction of a new Carlsborg Station 33. (Matthew Nash/Olympic Peninsula News Group file)
District sells one fire station

Commissioners approve 2025 budget

Clallam County Master Gardener Gordon Clark cuts leaves off Isobel Johnston’s agave plant that she had been growing for 28-plus years. She specifically requested Master Gardeners help her remove the plant while keeping at least one for years to come. (Matthew Nash/Olympic Peninsula News Group)
Master Gardeners help remove agave plant on Fifth Avenue

Several baby plants uncovered below large leaves

Harvey Hochstetter tosses a box of food to Cameron Needham to stack with fellow volunteers like Bill Needham, right, for the Sequim Food Bank’s Holiday Meal Bag Distribution event. Cameron, his father Ty and grandfather Bill were three generations helping the program. (Matthew Nash/Olympic Peninsula News Group)
Sequim Thanksgiving program helps 1,200 families

About 30 volunteers pack holiday boxes

Security exercise set at Indian Island

Naval Magazine Indian Island will conduct a security training… Continue reading

Operations scheduled at Bentinck range this week

Training at the land-based demolition range on Bentinck Island… Continue reading

Weekly flight operations scheduled

There will be field carrier landing practice operations for aircraft… Continue reading