Hood Canal Bridge pontoons due to be floated today

  • Monday, December 18, 2006 12:01am
  • News

TACOMA — The first three huge concrete pontoons built in Tacoma to replace part of the Hood Canal Bridge are set to be towed to Seattle, with two scheduled to leave today.

Tugs will tow the 8,300-ton concrete pontoons from their temporary mooring facilities in Tacoma’s Blair Waterway to Seattle’s Pier 66, according to Sarah Lamb of the state Department of Transportation, in a written statement.

The pontoons, the first of 14 to be built, were floated into the waterway out of Concrete Technologies’ graving yard by Transportation and project contractor Kiewit-General of Poulsbo on Dec. 6.

ADVERTISEMENT
0 seconds of 0 secondsVolume 0%
Press shift question mark to access a list of keyboard shortcuts
00:00
00:00
00:00
 

Each 35-mile tow will take approximately 17 hours. The pontoons will be towed at a rate of 2 mph.

Weather-dependent

Tows are dependent upon the weather.

The third pontoon is scheduled to be towed to Seattle next week.

The floating Hood Canal Bridge, which opened in 1961, is the lifeline for food, fuel and tourists to the North Olympic Peninsula, linking it with the Kitsap Peninsula and the Puget Sound area.

More in News

Caro Tchannie and her daughter Lola Hatch, 9, of Tulallip try a long string of beads at Squatchcon on Thursday at the Vern Burton Community Center gym in Port Angeles. Kevin VanDinter of Port Angeles was one of 60 vendors at the four day event, which continues through Sunday. (Dave Logan/for Peninsula Daily News)
Squatchcon underway

Caro Tchannie and her daughter Lola Hatch, 9, of Tulallip try a… Continue reading

Capital budgets include Peninsula

Millions in state funds earmarked

Mike Chapman.
Chapman asks not to employ legislative privilege

State senator removes an exemption to Public Records Act

Port of Port Townsend considering Short’s Farm access

Commissioners aim to balance public, agricultural use

Jefferson library director to start new job May 19

Meet-and-greet event scheduled for May 22

Man taken to hospital after car hits tree

A man was transported to a hospital after a single-car… Continue reading

Bypass roads to be installed at two fish passage sites

Contractors will begin construction of one-lane bypass roads at two… Continue reading

Emily Matthiessen/Olympic Peninsula News Group
Stew Cockburn stands in the spring annual section prior to it being for early spring gardeners.
New Dungeness Nursery planted in landscaping industry

Family and their employees work 2-acre location in Sequim

Partnership discussion may violate state law

OMC in Phase 2 of exploratory process

Members of the public take a guided tour at Port Townsend High School on Wednesday. (Elijah Sussman/Peninsula Daily News)
Port Townsend school district may seek $90M bond

Tour highlights high school’s infrastructure needs

A pair of wind surfers take off from the breakwater at Port Townsend Marina in an apparent race across the bay on Tuesday. (Steve Mullensky/for Peninsula Daily News)
Catching the wind

A pair of wind surfers take off from the breakwater at Port… Continue reading