It all depends on the weather, says manager

PORT ANGELES — Completion of the two Eighth Street bridges is dependent on the weather, the Exeltech construction manager said.

Long Painting of Kent, which is sub-contracted by the construction company Parsons RCI of Sumner, must have good enough conditions to finish applying a sealer to the concrete bridges.

Because of unfit weather conditions, Ingo Goller, Exeltech construction manager, couldn’t say on Thursday when the bridges will open to vehicles and pedestrians.

The city of Port Angeles hired Exeltech to manage the project.

The project, which began in June 2007, is funded by $21.6 million in state Department of Transportation grants and $3 million in city funds.

It was initially set to be complete in November.

Glenn Cutler, city public works director, has said that Parsons was given a 45-working-day contract extension for a redesign of a foundation abutment on the west side of the Tumwater Creek bridge due to what he referred to as “poor soil.”

The extension cost the city $90,000, he said, and other delays have resulted from poor weather.

When asked how much longer construction will last, Goller could only refer to the 16 days Parsons has left in its contracted working days.

If company employees are able to work every weekday, that would put completion of the project at Feb. 20.

But that seems unlikely because of stringent weather requirements for applyng the sealer.

The sealer is meant to protect the concrete from moisture and make it easier for spray paint to be washed off.

Goller said that applying the sealer requires a minimum air temperature of 35 degrees, less than 85 percent humidity and a dewpoint no more than five points more than the minimal air temperature.

Even Thursday’s weather, which was sunny and fairly warm in Port Angeles, wasn’t good enough, because rain was predicted for the afternoon and the sealer needs four hours to dry, he said.

About 30 percent of the concrete has been covered by the sealer, Goller said, and Parsons needs about eight days of good weather during a Monday through Friday work week to complete the work.

Goller said the city would have to reimburse Parsons for overtime pay if the work is done during a weekend.

Do it later?

So why not open the bridges and do sealer work later?

City officials had thought of that and scheduled a meeting for last Wednesday with Parsons and Exeltech on that topic.

Goller said the meeting wasn’t held this week because the project manager for Parsons was too sick to make it. He said the meeting probably will be next Wednesday.

Goller said an issue that needs to be resolved for the bridges to open before the contracted work — such as the applying the sealer –is finished, is safety liability.

“As long as the contractor has the contract in his hands and the schedule of work has not been completed, the liability is the contractor’s,” he said.

“Liability shifts when it’s in public use.”

Goller said that the city of Port Angeles would have to resolve that issue with Parsons for the bridges to be opened before the sealer work can be completed.

What certainly has to be completed before the bridges can be opened is the installation of the railing.

Goller said the railing is almost completely installed and will be completed as soon as Parsons receives a few more pieces, which had to be specially ordered.

“The normal procedure is to put all the rail in that we can, and the unique pieces, to make everything fit right, are field-measured and ordered,” he said.

Goller said that, once the pieces are delivered, completion of the railing work will take one day.

________

Reporter Tom Callis can be reached at 360-417-3532 or at tom.callis@peninsuladailynews.com.

More in News

Commander R.J. Jameson, center, exits the change of command ceremony following his assumption of the role on Friday at the American Legion Hall in Port Townsend. (Elijah Sussman/Peninsula Daily News)
Naval Magazine Indian Island sees change in command

Cmdr. R.J. Jameson steps into role after duties across world

Allen Chen.
Physician officer goes back to roots

OMC’s new hire aims to build services

f
Readers give $111K in donations to Home Fund

Donations can be made for community grants this spring

A ship passes by Mount Baker in the Strait of Juan de Fuca as seen from the Port Angeles City Pier on Wednesday morning. The weather forecast continues to be chilly this week as overnight temperatures are expected to hover around freezing. Daytime highs are expected to be in the mid-40s through the weekend. (Dave Logan/for Peninsula Daily News)
Off in the distance …

A ship passes by Mount Baker in the Strait of Juan de… Continue reading

Creative District to transfer to PT

Creating year-round arts economy program’s goal

Officers elected to Port of PT’s Industrial Development Corporation

Surveyor to determine value of 1890 wooden tugboat

Clallam County to install anti-human trafficking signs

Prosecuting attorney to challenge other jurisdictions to follow suit

Portion of Old Olympic Highway to be resurfaced

Project will cost about $951,000

Dona Cloud and Kathy Estes, who call themselves the “Garbage Grannies,” volunteer each Wednesday to pick up trash near their neighborhood on the west side of Port Angeles. They have been friends for years and said they have been doing their part to keep the city clean for five years now. (Dave Logan/for Peninsula Daily News)
Garbage grannies

Dona Cloud and Kathy Estes, who call themselves the “Garbage Grannies,” volunteer… Continue reading

Director: OlyCAP’s services contributed $3.4M in 2024

Nonprofit provided weatherization updates, energy and utility assistance

Clallam Transit purchases vehicles for interlink service

Total ridership in December was highest in seven years, official says