Judge permits timber harvest that environmentalists claim threatens marbled murrelet in Clallam and Jefferson counties

The marbled murrelet was at the center of a recent request to halt logging planned by Interfor. National Audubon Society

The marbled murrelet was at the center of a recent request to halt logging planned by Interfor. National Audubon Society

PORT TOWNSEND — A Jefferson County judge has rejected a request for a temporary injunction against a state-approved harvest of 234 acres of timber on the West End adjacent to habitat of the threatened marbled murrelet.

After an hourlong presentation last week from attorneys on both sides of the issue, Jefferson County Superior Court Judge Keith Harper ruled against the plaintiffs, permitting the timber harvest by Interfor, which has mills in Forks and Port Angeles.

The judge ruled Friday that the area in question is outside of the murrelet’s habitat and that the plaintiffs could have filed an action in advance of the beginning of the logging operation, which had been scheduled to begin Saturday.

ADVERTISEMENT
0 seconds of 0 secondsVolume 0%
Press shift question mark to access a list of keyboard shortcuts
00:00
00:00
00:00
 

The injunction request, filed by the Seattle Audubon Society and the Olympic Forest Coalition, sought to prevent the scheduled logging of 234 acres of timber in the state Department of Natural Resources’ Goodmint and Rainbow Rock sites in west Clallam and Jefferson counties south of Forks.

Environmentalists said that the area had been set aside under the state’s marbeled murrelet habitat conservation plan with the federal government.

The marbled murrelet, a member of the auk family, is listed as a threatened species under the federal Endangered Species Act.

The units are second-growth timber surrounded by old-growth forests.

Old-growth forests trees near the ocean are considered critical habitat for the small seabird’s nesting habitat.

State officials said the second-growth trees in question are not vital to the murrelet’s habitat, while Interfor said the trees are badly needed to supply the company’s mill in Beaver and delays are costing jobs.

The environmental groups argued that while the area in question was not the old growth forest where the endangered bird usually lives, its proximity made it an important habitat for the bird.

The ruling “was a big disappointment,” said Monica Fletcher, chairwoman of the North Olympic Peninsula chapter of the Sierra Club.

“This bird has really relied on old growth but needs a contiguous area to survive.

“The bird is under assault from the land and the sea and we need to keep going on this.”

Harper disagreed, saying that it was clear the area was not within the habitat and the logging can proceed.

Wyatt Golden, an attorney for the plaintiffs,’ said the last-minute timing of the injunction was because the plaintiffs were exhausting all other options.

Harper disagreed, stating “plaintiffs could have filed an action months ago.”

Approving the injunction would cause the logging company, Interfor, a lumber company with mills in Forks and Port Angeles, to lose money on its investment of $2,126,413 for the timber, Elaine Spencer, an attorney representing Interfor, told the judge.

The company bid in April $1,420,411 for the timber from the Goodmint unit in Jefferson and Clallam counties and $706,002 for the Rainbow Rock timber in Jefferson County, she said.

The bids were based on prices that could fall if the logging is delayed, Spencer said, so delay could cost the company money.

“These bids are based on current prices and could be quite different next summer,” said Spencer.

She added that 81 jobs are connected to the logging operation.

Golden responded that “the harm suffered to the environment is irrevocable while the economic harm is temporary.”

The logging action is taking place without an Environmental Impact Statement.

Sometimes such a statement is required under the State Environmental Policy Act, but, said DNR attorney Paul Lawrence, not in this case, a position Harper supported.

Plaintiffs’ attorney Peter Goldman disagreed.

“This is a radical departure from DNR’s normal way of dealing with timber sales,” he said after the hearing.

“DNR generally does SEPA for every timber sale.

“What’s very concerning is that if DNR is taking a new position, that is very concerning to the conservation community.”

Friday’s ruling doesn’t affect pending lawsuits to stop the harvests but “removes the urgency” in that action.

“This is just 230 acres but is representative of thousands of acres that were identified for marbled murrelet conservation that are now at risk,” Goldman said.

“It doesn’t set a legal precedent but it gives DNR a green light to log habitat that was identified for conservation.”

Ann Forest Burns, vice president of the American Forest Resource Council, said she was pleased by the decision.

Granting the injunction would have set a different precedent, she said.

“If this was granted, then no landowner would ever want to enter into a deal with the government,” she said.

“They would see that every time an environmental group doesn’t like a timber sale, they can file an injunction.”

On May 30, the state announced the harvest could begin as of June 13.

“The timber in the Goodmint and Rainbow Rock sales is relatively immature. There is no marbled murrelet habitat in these sales, and we are protecting the nearby habitat with a buffer nearly double the width of what’s required of private landowners in Washington,” Kyle Blum, DNR’s deputy supervisor for state uplands, said then.

Revenue from DNR land goes to schools, universities, county governments and other public institutions. The Board of Natural Resources sets policies for land management and approves timber sales.

While Harper’s action cleared the way for logging to begin on Saturday it was unclear whether this would occur “as many of those involved might be working on other projects,” Burns said.

________

Jefferson County Editor Charlie Bermant can be reached at 360-385-2335 or charlie.bermant@peninsuladailynews.com.

Sequim-Dungeness Valley Editor Joe Smillie contributed to this story.

More in News

A public fireworks display at Carrie Blake Community Park on Independence Day, as pictured in 2022, will be discussed tonight at the Sequim City Council meeting. The discussion follows public requests to stop the display due to potential impact on wildlife and residents. (Michael Dashiell/Olympic Peninsula News Group file)
Sequim council to hear analysis

Staff to discuss fireworks impacts

North Olympic Library System
North Olympic Library System representatives reported in late March that drywall was going up inside the renovated Sequim Library. However, delivery delays for some windows and other elements have pushed the facility’s opening to late July or early August.
Library expansion opening pushed to mid-summer

Custom elements’ deliveries delayed

Portion of Olympic Discovery Trail closed for three weeks

The city of Port Angeles has closed a portion… Continue reading

No training flights scheduled for this week

There will be no field carrier landing practice operations for… Continue reading

Fred Lundahl, a pilot from Whidbey Island, prepares to fuel up his 1968 Cessna Aerobat, named Scarlett, at the Jefferson County International Airport in Port Townsend. Lundahl was picking up his plane Wednesday from Tailspin Tommy’s Aircraft Repair facility located at the airport. (Steve Mullensky/for Peninsula Daily News)
Fueling up

Fred Lundahl, a pilot from Whidbey Island, prepares to fuel up his… Continue reading

After hours pet clinic set for Peninsula

Opening June 6 at Sequim location

Five to be honored with community service awards

Ceremony set Thursday at Port Angeles Senior Community Center

PASD planning for expanding needs

Special education, homelessness, new facilities under discussion

Clallam County Sheriff’s Office Animal Control Deputy Ed Bauck
Clallam Sheriff appoints animal control deputy

Position was vacant since end of 2024

Highway 104 road work to start week

Maintenance crews will repair road surfaces on state Highway… Continue reading

Supreme Court says no to recall reconsider

Sequim man found liable for legal fees