What remains of Glines Canyon Dam

What remains of Glines Canyon Dam

More repairs needed at Port Angeles water plant, will likely hold up Elwha River dam removal work

PORT ANGELES — Additional repairs are needed for the sediment-clogged Elwha Water Treatment Plant on the Elwha River, and that could push the removal of the remaining 60 feet of Glines Canyon Dam past the initially estimated July 1 resumption date, an Olympic National Park spokeswoman said.

Earlier this year, National Park Service staff determined that the backup intake at the water plant, which is 2.8 miles from the river’s mouth, needs new sediment-filtering fish screens, and two of six screens have been replaced by National Park Service contractor Macnak Construction.

Work halted in April, however, after river sediment unexpectedly began flowing into the Elwha Water Treatment Plant — which was built to filter sediment from water before it is treated for the Port Angeles water supply — and reached components not designed to ever handle the material.

Park Service engineers also have determined the pump station’s pipes will not be able to handle the amount of sediment in the river, Olympic National Park spokeswoman Barb Maynes said.

So additional repairs are needed for the pumping station that pulls Elwha River water from the water plant’s backup intake into the plant itself, she said.

The water-treatment plant is part of the National Park Service’s $325 million restoration of the Elwha River, begun in September 2011.

The project includes the removal of two antiquated dams that blocked fish passage and stopped sediment transport on the 45-mile-long river a century ago.

An estimated 6 million cubic yards of sediment — of about 34 million cubic yards trapped by the dams — have flowed down the river as result of the removal of Elwha Dam, completed last March, and the demolition of Glines Canyon Dam, which has been stopped since October.

The initial hiatus was a “fish window” to protect fish migration. That was first extended in January because of sediment problems at the plant, and the latest date for resumption of work was set for July 1.

“It’s likely that will change,” Maynes said Friday.

“If dam removal is deferred until after July, then the earliest it can start after that is not until mid-September.”

This is because dam-removal contractor Barnard Construction would have to abide by another fish window set to start Aug. 1 and end Sept. 15.

“We’re still looking at the project being completed within the contract period, which takes us through September 2014, but a timeline within that hasn’t been set,” Maynes said.

Designs for fixes for the pump station and its pipes are in preliminary phases, Maynes said, adding that she could not provide an estimate on cost or how long installing them might take.

The Elwha Water Treatment Plant was designed to filter water inundated with sediment to a certain degree and pass it along for use by four downstream users: Nippon Paper Industries USA, the state Department of Fish and Wildlife fish-rearing channel built along the river, the Lower Elwha Klallam tribe’s fish hatchery and the Port Angeles Water Treatment Plant, which provides drinking water for the city.

Since fall, however, the plant has not been able to provide enough filtered water to these users.

The city has had to pull more water from its primary water source, called the Ranney well, than expected.

Officials are concerned that ultimately could shorten the life of the decades-old facility.

The Ranney well, however, is continuing to do its job of supplying enough water for city residents and businesses, said Glenn Cutler, Port Angeles public works director, on Friday.

Sediment has been seen inundating the shoreline of the river tributary that leads to the Ranney well.

The city’s concerns over use of the Ranney Well and the need for additional fixes to the treatment plant were discussed at a Thursday meeting between city and Park Service staff — which included U.S. Department of the Interior Office of the Solicitor attorney-advisers William Back and Kelly Powell.

City Manager Dan McKeen said Friday the meeting established lines of communication between city staff and the Park Service over how Park Service staff are addressing the problems at the Elwha Water Treatment Plant, which with its surface water intake is collectively referred to as the Elwha Water Facilities.

“We felt it was a very beneficial meeting,” McKeen said, adding that more meetings are expected.

Cutler said city engineering staff shared data on the Ranney well’s operation with national park engineers.

The city will provide input to the park as the problems with the Elwha Water Treatment Plant are corrected, he said.

Other city staff members attending were attorney Bill Bloor, City Engineer Mike Puntenney and water superintendent Ernie Klimek.

Park Service staff in attendance were Maynes, Olympic National Park Superintendent Sarah Creachbaum, Elwha River Restoration project manager Brian Winter and the National Park Service’s Denver Service Center Elwha project manager, Karl von Rosenberg.

“There was a very good discussion [at the meeting], and a lot of cooperation was displayed,” Creachbaum said later.

Powell and Back were among the Solicitor’s Office attorneys who signed an April 17 emailed memo titled “Communication Containing Work Product in Anticipation of Litigation” that was sent to 16 Park Service employees, including von Rosenberg, Winter, Maynes and Creachbaum.

According to a copy of the email obtained by the Peninsula Daily News, Interior officials are preparing for possible legal action over alleged design flaws at the Elwha treatment plant that have caused “significant damage and delay.”

The Solicitor’s Office, the Interior’s legal branch, said its staff is “investigating the design deficiency issue of [Elwha Water Facilities] and anticipates legal action may result.”

Sediment and woody debris have not been removed from the water facilities and surface water intake “as designed,” it said.

San Francisco-based URS Corp., the engineering, construction and technical services company that designed the Elwha Water Facilities, “has denied responsibility for the problems that are occurring at EWF,” the memo said.

URS Corp. spokeswoman Pam Blum said Friday the company had no comment on potential legal action involving the water facilities.

Solicitor’s Office attorney-adviser Stephanie Lynch would not comment last week on the memo.

________

Reporter Jeremy Schwartz can be reached at 360-452-2345, ext. 5074, or at jschwartz@peninsuladailynews.com.

Senior Staff Writer Paul Gottlieb can be reached at 360-452-2345, ext. 5060, or at paul.gottlieb@peninsuladailynews.com.

More in News

A member of the First Night Circus performs her routine at the American Legion Hall in Port Townsend during the First Night activities produced by the Production alliance on New Year’s Eve. (Steve Mullensky/for Peninsula Daily News)
First Night festivities

A member of the First Night Circus performs her routine at the… Continue reading

Dave Neupert.
Judge becomes Clallam coroner

Charter still must be amended

The Upper Hoh Road is closed at milepost 9.7 after heavier flows eroded pavement.
Upper Hoh Road closed after river erodes pavement

Jefferson County lacks funding for immediate repair, official says

Port of Port Angeles to discuss surplus of property

The Port of Port Angeles will hold the first… Continue reading

Todd Shay of the Port Angeles Parks and Recreation Department lowers the flags in front of City Hall on Monday to honor Jimmy Carter, the 39th president of the United States who died Sunday at the age of 100. The flags will stay at half-staff until the end of the day Jan. 28 by order of the governor. (Dave Logan/for Peninsula Daily News)
Honoring President Carter

Todd Shay of the Port Angeles Parks and Recreation Department lowers the… Continue reading

911 call center making changes

Traveling dispatchers, AI part of solutions

Jefferson County grants $800K in lodging tax

Visitor center, historical society among applicants

Colleges ‘not optimisic’ on state financial error

Peninsula College would owe $339,000

Wednesday’s e-edition to be printed Thursday

Peninsula Daily News will have an electronic edition on… Continue reading

Volunteers sought for annual Point in Time count

Olympic Community Action Programs is seeking volunteers to assist… Continue reading

Two men taken to hospitals after crash

Two men were taken to hospitals following a collision on… Continue reading

Coho to undergo scheduled maintenance

Black Ball Ferry Line’s M/V Coho ferry will be… Continue reading