A faulty boiler that delayed Nippon Paper Industries’ $85 million biomass cogeneration plant operations is carried by a crane earlier this year. — Nippon Paper Industries USA photo

A faulty boiler that delayed Nippon Paper Industries’ $85 million biomass cogeneration plant operations is carried by a crane earlier this year. — Nippon Paper Industries USA photo

Nippon biomass cogeneration plant targets Nov. 1 start

PORT ANGELES — Work could wrap up in the next several weeks on Nippon Paper Industries USA’s long-stalled biomass cogeneration plant.

The expectation is that it will be up and running full bore by Nov. 1.

“We hope to beat that,” Steve Johnson, mill manager, said last week. “We have several weeks of work left.”

Tests on the new boiler mud drum that was installed in early September will result in a steam plume expected to issue from the plant at Ediz Hook later this week, Johnson said.

If the Nov. 1 finish date holds, the cogeneration plant will be fully operational nearly a year after the project was slated to begin producing steam for the mill and 20 megawatts of electricity for the mill and for sale to buyers of green energy.

The Tokyo-based company had made agreements with buyers who wanted to purchase the cogeneration plant’s electricity.

Nippon has made good on the commitments by purchasing electricity on its own and reselling it to those buyers.

“We did what was right by our customers,” Johnson said.

“We made a commitment, and we honored it.”

The project, expected to exceed $85 million, was dedicated during a ceremony at the papermaking plant Nov. 1, 2013, with the expectation is would be operational later

that month.

But cracks were discovered in the plant boiler’s mud drum, a 30-foot, 25-ton pressurized vessel that collects solids from the boiler drum, and the plant has never operated at capacity.

The mud drum and 40,000 feet of tubing have since been replaced in repairs that have boosted the cost of the project, which had been estimated at $71 million in 2010 and rose 20 percent to $85 million by 2013.

Johnson would not disclose the current cost but said it will be “comfortably” under $90 million.

The project upgrades the existing cogeneration plant, which has an antiquated boiler that uses biomass — woody debris such as forest slash and peeled bark — to produce only steam for the plant and is in use until the new boiler works.

Nippon, which produces telephone book paper and newsprint for the Peninsula Daily News and the weekly Sequim Gazette and Forks Forum, continues to employ about 200 workers and operate 24 hours a day, seven days a week, Johnson said.

“The support out of Tokyo and senior management has been outstanding,” he added.

“Certainly they’re disappointed in the delays, don’t get me wrong, but their support has been strong.”

Problems with the biomass plant first shut it down completely in February.

Nippon and Covington, La.-based FSE Energy, the primary contractor for the cogeneration plant project, expect to undergo mediation to determine who will cover repair and replacement costs, Johnson said.

“We’re still waiting on the contractor to get back to us, and we can meet in mediation,” he said.

Earlier this summer, a hole was cut in the side of the boiler and the cracked mud drum rolled out on a steel jig before being placed on the ground.

The new mud drum “went in exactly the same way” the old component came out, Johnson said.

On Sept. 8, the boiler was filled with water, pressure was applied, and their were no leaks.

The boiler can produce 225,000 pounds of steam.

“There are still many weeks to go, but it was a big milestone, if you will,” Johnson said.

The boiler wall was replaced the weekend of Sept. 13, and the internal surface was chemically cleaned by Friday.

Port Townsend Paper Corp. earlier this year abandoned a much-disputed $54 million project to upgrade its own cogeneration plant that would have generated 24 megawatts.

Both projects survived numerous environmental challenges.

But those challenges slowed down the Port Townsend project and, combined with a strong market for cheap natural gas, were a factor in dooming it, company President Roger Hagan told Peninsula Daily News earlier this year.

The cracked mud drum and 1,600 steam tubes from Nippon’s cogeneration project will remain in the mill’s parking lot for the time being.

“We’re obviously saving those for arbitration,” Johnson said.

________

Senior Staff Writer Paul Gottlieb can be reached at 360-452-2345, ext. 5060, or at pgottlieb@peninsuladailynews.com.

More in News

John Gatchet of Gardiner, left, and Mike Tabak of Vancouver, B.C., use their high-powered scopes to try to spot an Arctic loon. The recent Audubon Christmas Bird Count reported the sighting of the bird locally so these bird enthusiasts went to the base of Ediz Hook in search of the loon on Sunday afternoon. (Dave Logan/for Peninsula Daily News)
Bird watchers

John Gatchet of Gardiner, left, and Mike Tabak of Vancouver, B.C., use… Continue reading

Forks schools to ask for levy

Measure on Feb. 11 special election ballot

Jefferson County commissioners name Pernsteiner acting sheriff

Jefferson Democrats to nominate three interim candidates

State commission fines fire commissioner

PDC says Kraft owes more than $4,600

Marine Center receives $15 million

Funding comes from Inflation Reduction Act

Port Townsend creates new department to oversee creative district

Melody Sky Weaver appointed director of Community Service Department

Orca that carried dead calf for weeks is mourning again

The mother orca nudges her dead calf with her snout, draping it… Continue reading

Weekly flight operations scheduled

There will be field carrier landing practice operations for aircraft… Continue reading

Will Barrett of Port Townsend and his cairn terrier Harris brave the cold and wet weather on Friday to walk around the Marine Science Center pier at Fort Worden State Park. (Steve Mullensky/for Peninsula Daily News)
Rainy walk

Will Barrett of Port Townsend and his cairn terrier Harris brave the… Continue reading

Kate Dean.
Kate Dean reflects on Jefferson County career

Will work for state office of Public Lands

The Hub, a place to form community connections and incubate ideas, hosts a Night Market on the third Friday of every month. CEO Roxanne Greeson invited people to drop by for one of their events, or stop by between 10 a.m. and 8 p.m. Tuesday through Saturday, to see what they think of the space. (Roxanne Greeson)
The Hub aims to incubate ideas, grow community

PA business hosts spaces for artists, storefront to sell creations

Food resources are available across Peninsula

Officials say demand continues to rise over previous years