Nippon Paper mill workers back at Port Angeles facility; some systems still coming online

PORT ANGELES — Workers returned to the Nippon Paper Industries USA plant Sunday to bring the facility back into full operation after a two-week repair closure.

The plant, shuttered to work on the company’s $85 million biomass cogeneration plant, saw some systems up and running while others remained shut down as of Sunday afternoon, a union official said.

“Number 8, the old boiler, is running,” said Darrel Reetz, vice president of Association of Western Pulp & Paper Workers Local 155, on Sunday.

The biomass plant had not yet begun operating as of Sunday afternoon, but, “they’re getting things going,” Reetz said.

Crews encountered mechanical and electrical difficulties with several key systems in the paper plant itself Sunday — problems similar to those a car might have after not being used for some time, he said.

Reetz said he doesn’t expect the plant to be fully operational for at least a few days, as each system is restarted.

Plant Manager Harold Norlund has not returned calls for comment about the shutdown.

During the shutdown, 119 out of an estimated 200 plant employees were without work.

Reetz did not know how many employees returned to work Sunday.

Some employees were retained during the shutdown to perform routine maintenance on the paper plant’s equipment while the facility was inactive.

Employees received notice on Feb. 18 that a two-week scheduled maintenance shutdown scheduled for April was moved up to begin Feb. 23.

Those who were let go for the two weeks were allowed to take unused vacation time.

Others sought temporary employment or filed for unemployment.

Repairs to the new biomass boiler included new screws installed on the fuel system and upgrades to the boiler’s ash-processing system.

The shutdown was due to problems with the screws, which transport hog fuel, the woody logging debris used in biomass-fired plants.

The fuel was not adequately feeding the mill’s new boiler, Reetz said.

The biomass boilers burn wood waste to create steam for the plant, and the new boiler, installed in 2013, is designed to generate enough electricity to sell.

The biomass plant has the capacity to produce 20 megawatts, but has been able to produce only about half that amount.

________

Reporter Arwyn Rice can be reached at 360-452-2345, ext. 5070, or at arwyn.rice@peninsuladailynews.com.

More in News

Laurie Hutchings of Port Angeles, right, and her grandson, Regan Davis, 5, of Port Angeles examine a display of infant car seats as Crystal Clark, a volunteer car seat technician for the Sequim Police Department, describes their function during Saturday’s Public Safety Fair at the Guy Cole Convention Center at Carrie Blake Park in Sequim. The event featured a variety of public safety agencies and their equipment, as well as lectures and other presentations. (Keith Thorpe/Peninsula Daily News)
Safety fair

Laurie Hutchings of Port Angeles, right, and her grandson, Regan Davis, 5,… Continue reading

Counties consider timber models

Two distribution methods discussed

Respiratory illnesses trending down, public health officer says

COVID-19 and flu activity are low; RSV season not yet here

Two injured in collision on Highway 101 near casino

Two people were taken to hospitals following a collision on… Continue reading

A massive kinetic skulpture called Maxtivity’s GLORY-ous Chocolate Turtle from Corvallis, Ore., negotiates a turn on Water Street during the 40th Kinetic Skulpture Parade and Race in downtown Port Townsend on Saturday. (Steve Mullensky/for Peninsula Daily News)
Kinetic Skulpture race

A massive kinetic skulpture called Maxtivity’s GLORY-ous Chocolate Turtle from Corvallis, Ore.,… Continue reading

The fireworks display, seen over Carrie Blake Community Park on July 4, 2023, started after the ban on the discharge of fireworks in the city of Sequim. City council members host a public hearing on whether or not to ban the sale of fireworks on Oct. 14. (Michael Dashiell/Olympic Peninsula News Group)
Sequim to host fireworks hearing

City council to consider banning sales

Staff with PNNL-Sequim plan to expand the laboratory space by demolishing two temporary buildings by Washington Harbor along Sequim Bay and build a three-story structure. They also intend to add Sequim utilities along West Sequim Bay Road in the coming years. (Andrea Starr/Pacific Northwest National Laboratory)
PNNL-Sequim expansion linked to West Sequim Bay Road utility additions

City water, sewer improvements could go to bid mid-2025

Fire districts focus on smoke alarms during prevention week

Fire districts across Clallam and Jefferson counties are gearing… Continue reading

Weekly flight operations scheduled

There will be field carrier landing practice operations for aircraft… Continue reading

State and local officials toured Dabob Bay forests in 2022. Back row, left to right, Mary Jean Ryan of Quilcene; Rachel Bollens; Bill Taylor, Taylor Shellfish Co.; Jeromy Sullivan, Port Gamble S’Klallam Tribe; Justin Allegro, The Nature Conservancy; and Greg Brotherton, Jefferson County Commissioner. Front row, left to right, Duane Emmons, DNR staff; Jean Ball of Quilcene; Hilary Franz, state Commissioner of Public Lands; Mike Chapman, state Representative; and Peter Bahls, director of Northwest Watershed Institute. (Keith Lazelle)
Dabob Bay conservation area expands by nearly 4,000 acres

State, local partners collaborate on preservation effort

Three bond options on table for Sequim

School board considering February ballot

State EV rebate program proving to be popular

Peninsula dealerships participating in Commerce project