Officials outline Dungeness septic options, costs

SEQUIM –– With many of the decades-old septic systems that handle waste from homes in the Dungeness and Three Crabs neighborhoods leaking into the waters that feed Dungeness Bay, officials are looking into the need for a new community sewer system.

Options for replacing the current septic systems range in cost from $13 million to $25 million, Damon McAlister with the Parametrix engineering firm of Bremerton — which has developed a draft Dungeness Wastewater Treatment Feasibility Study — told landowners at a meeting at the Dungeness Schoolhouse on Saturday morning.

Ann Soule with the Clallam County Environmental Health Department said the county was awarded a grant from the state Department of Ecology last year to develop a plan to improve the quality of Dungeness Bay’s water.

The goal is to come up with a plan that would treat sewage from the north shore neighborhoods to a level that would reduce fecal coliform contamination, improve habitat for salmonids and allow the bay to be reopened to shellfishing.

“This is the kind of search for an elegant solution to a problem that I just love,” Clallam County Commissioner Jim McEntire said after the meeting.

The county says on its website, http://tinyurl.com/brwwrjq, that microbial source tracking in the Dungeness Bay shellfish growing area adjacent to this community — portions of which are closed for commercial harvest — “shows that human waste is a contributor to water quality degradation.”

It also says that failing to deal with septic system problems could lead to lower property values.

McAlister presented a handful of landowners and officials in attendance Saturday with four options: replace aging septic tanks with more modern systems; install smaller sewer systems for clusters of houses; have a large, centralized system to collect and treat wastewater; or develop a central collection system that would pump the sewage to Sequim for treatment.

“Each has its pros and cons,” McAlister said.

“What we’re trying to determine is what would provide the most benefit for the least cost.”

McAlister’s presentation Saturday listed a range of prices from a low of $13 million for new septic systems for each lot all the way up to $25 million, which would be the cost for the central collection and treatment option.

Treated water must come out as a Class A effluent, McAlister said, which means it would be suitable to irrigate land but will not be consumed by humans.

Unless a grant is acquired to help pay for the construction, the cost of the upgraded sewer system would be borne by land owners.

The most expensive option would mean the average cost to lot owners would be up to $46,860.

Matt Heins of Dungeness Farms, though, noted the cost could be factored based on lot size or other figures that would require larger lot owners, like him, to pay more.

He said the cost would be worth it, however.

Dungeness Farms would eventually be able to use a commercial shellfish license it hasn’t been able to use for 15 years because of the pollution in the bay, he said.

The Clallam County health department held a pair of public hearings on the sewage dilemma last year, collecting surveys from residents who said improving the quality of the Dungeness Bay was their top priority.

Another public hearing probably will be held in March before a final draft of the feasibility study is presented to Clallam County commissioners later this year, county personnel said.

See the county website for the draft feasibility study.

Sequim-Dungeness Valley Editor Joe Smillie can be reached at 360-681-2390, ext. 5052, or at jsmillie@peninsuladailynews.com.

More in News

Two people were displaced after a house fire in the 4700 block of West Valley Road in Chimacum on Thursday. No injuries were reported. (East Jefferson Fire Rescue)
Two displaced after Chimacum house fire

One person evacuated safely along with two pets from a… Continue reading

A Port Angeles city worker places a tree topper on the city’s Christmas tree, located at the Conrad Dyar Memorial Fountain at the intersection of Laurel and First streets. A holiday street party is scheduled to take place in downtown Port Angeles from noon to 7 p.m. Nov. 30 with the tree lighting scheduled for about 5 p.m. (Emma Maple/Peninsula Daily News)
Top of the town

A Port Angeles city worker places a tree topper on the city’s… Continue reading

Hospital board passes budget

OMC projecting a $2.9 million deficit

Lighthouse keeper Mel Carter next to the original 1879 Fresnel lens in the lamp room at the Point Wilson Lighthouse. (Elijah Sussman/Peninsula Daily News)
Donations to aid pediatrics clinic, workforce

Recipients thank donors at hospital commissioners’ meeting

Whitefeather Way intersection closed at Highway 101

Construction crews have closed the intersection of Whitefeather Way and… Continue reading

EYE ON THE PENINSULA: Commissioners to consider levies, budgets

Meetings across the North Olympic Peninsula

Highway 112 partially reopens to single-lane traffic

Maintenance crews have reopened state Highway 112 between Sekiu… Continue reading

Laken Folsom, a Winter Ice Village employee, tries to remove leaves that blew in from this week’s wind storm before they freeze into the surface of the rink on Thursday. The Winter Ice Village, operated by the Port Angeles Chamber of Commerce in the 100 block of West Front Street, opens today and runs through Jan. 5. Hours are from noon to 9 p.m. daily. New this year is camera showing the current ice village conditions at www.skatecam.org. (Dave Logan/for Peninsula Daily News)
Ice village opens in Port Angeles

Laken Folsom, a Winter Ice Village employee, tries to remove leaves that… Continue reading

Fort PDA receiver protecting assets

Principal: New revenue streams needed

Ella Biss, 4, sits next to her adoptive mother, Alexis Biss, as they wait in Clallam County Family Court on Thursday for the commencement of the ceremony that will formalize the adoption of Ella and her 9-year-old brother John. (Emma Maple/Peninsula Daily News)
Adoption ceremony highlights need for Peninsula foster families

State department says there’s a lack of foster homes for older children, babies

Legislature to decide fate of miscalculation

Peninsula College may have to repay $339K