Port Angeles’ Eighth Street bridges now expected to open in February

PORT ANGELES — The long-awaited completion of the Eighth Street bridges will take a little longer.

The city of Port Angeles and project manager, Exeltech, estimate the two concrete bridges will be open to traffic and pedestrians on about Feb. 2, as long as there are no weather-related delays.

The project is still within its $24.6 million budget, but construction company, Parsons RCI of Sumner, is in the process of placing a request for additional funds to cover a significant increase in costs of materials since the project began, said Glenn Cutler, city public works director, on Tuesday.

Cutler said Parsons’ request will be reviewed, and if approved, he doesn’t expect it to cost more than $100,000 ¬­– which would still leave the project within budget.

As of Tuesday, the Tumwater Creek bridge is about 90 percent completed and the Valley Creek bridge is about 85 percent done, said Ingo Goller, Exeltech construction manager.

Construction began on June 25, 2007. Traffic has been rerouted through town to avoid the major arterial that crosses the two ravines.

The project is funded by $21.6 million in state Department of Transportation grants and $3 million in city funds.

45-day extension

Cutler said the project’s completion was most recently estimated for mid-December, but the city gave Parsons an extension of about 45-calendar days.

“Poor soil” on the west side of the Tumwater Creek bridge required a redesign of a foundation abutment that resulted in the extension, he said.

Cutler said Parsons received about $90,000 to cover the additional work.

Without any delays, Goller said the project could have been completed on Nov. 17.

Other than the contract extension, most of the other delays have been weather-related, he said.

Goller said Parsons’ $18.4 million contract awarded in April 2007 for construction of the new bridges, as well as demolition of the old timber trestle bridges, covers 350 working days.

Without the extension, the company would have about 10 more working days to go.

Under the current schedule, the work will last for about 19 months in total, which is the amount of work the city estimated when it put the project out to bid in December 2005.

The bridges will be 47 feet wide with two 12-foot lanes, two 5-foot bicycle lanes, two 6.5-foot sidewalks and two pedestrian viewpoints. They replace the two timber trestle bridges built in 1936.

Cutler said the new bridges have an estimated lifespan of 75 years.

Goller and Cutler both said that the project has gone “extraordinarily well.”

Said Cutler: “There have been no lost-time accidents. Parsons has an excellent safety record.

“There have been minimum traffic disturbances. We acknowledge there was some. . . it has been executed as expected.”

What’s left to do?

Goller said both bridges are substantially completed, and some cleanup work on the construction site has begun.

Most of the work left to do on the Vine Creek bridge, Goller said, includes the construction of sidewalks, placement of the railing on each side, spraying of a coat of “pigmented sealer” on the concrete, and site restoration.

Site restoration includes creation of wetlands in the valleys and the loosening of soil that has been compacted by the large construction vehicles.

Goller said the sealer prevents moisture from accessing the concrete, and also makes it easier for graffiti to be washed off.

Most of the work left to be done on the Tumwater Creek bridge, which is the closest to completion, includes placement of the railing, a coat of the sealer, and site restoration.

Other costs

On top of Parsons’ contract, a contingency fund, and planning costs, the project includes:

•âÇ$1.94 million contract with Exeltech for construction management.

•âÇ$175,000 for traffic signals.

•âÇ$70,000 for Clallam Transit and Paratransit to transport people to one side of the bridges to the other during construction.

________

Reporter Tom Callis can be reached at 360-417-3532 or tom.callis@peninsuladailynews.com.

More in News

A street sweeper on I Street in Port Angeles cleans up the street along the curbs of all the debris that blew down during Tuesday evening’s storm. Thousands were without power at the peak of the storm. (Dave Logan/for Peninsula Daily News)
Storm causes power outages, road closures

Smaller weather system may hit Friday

Port Angeles funds lodging tax requests

Sixteen applications to undergo review

Port Townsend’s Water Street sewer project gets funds

City council authorizes contracts; construction to start in January

Port of Port Angeles commissioners approve 2025 budget

Board OKs project that would treat seawater to make it less acidic

Two injured after truck collides with tree

Two people were injured when the truck in which… Continue reading

Power out for thousands in Clallam County

More than 11,000 electric meters were without power in… Continue reading

Shay-Lyn Szczepanik and her daughter Raelynn, 5, of Port Angeles are wind blown as they try to watch the wild waves at the base of Ediz Hook on Tuesday as the storm approaches. Many other weather watchers went to the spit to see and feel the winds. (Dave Logan/for Peninsula Daily News)
Storm surge

Shay-Lyn Szczepanik and her daughter Raelynn, 5, of Port Angeles are wind… Continue reading

Fire Marshal and floodplain administrator Phil Cecere answers questions with deputy floodplain administrator Greg Ballard on Monday night in Brinnon. (Elijah Sussman/Peninsula Daily News)
Jefferson commissioners update flood code

More than 70 people attend hearing in Brinnon

PASD board accepts Brewer’s resignation

School officials highlight performance of Native American students

Port Angeles lifts Stage III water restrictions

The city of Port Angeles has lifted all of… Continue reading

Chipotle Mexican Grill opens today at 2021, Suite B, U.S. Highway 101 in Port Angeles. The fast food restaurant features freshly prepared burritos, burrito bowls, salads and tacos. (Dave Logan/for Peninsula Daily News)
Chipotle opens in Port Angeles

Chipotle Mexican Grill opens today at 2021, Suite B, U.S. Highway 101… Continue reading

Agnes Kioko and Regina Mbaluku of Kenya and Bonita Piper, board president of Path From Poverty, right, meet with Sequim volunteers who cut and sell wood as a fundraiser. (Michael Dashiell/Olympic Peninsula News Group)
Connection helps Kenyan women with opportunities, relationships

This effort, gifts from thousands of miles away, aren’t just… Continue reading