Port of Port Angeles to use dredging material for industrial park

Polluted sediment set to become fill

PORT ANGELES — Shoreline-area sediment too polluted for open-water disposal, as had been planned by the Port of Port Angeles, will be used instead as fill material for the port’s Marine Industrial Park.

The change in fate for the sediment could cause a “significant cost overrun” for the Port’s Terminal 3 dredging project, which had been budgeted for $1.1 million and could “go upward of $1.5 million,” if it’s too polluted for upland disposal, port Director of Engineering Chris Hartman said Tuesday.

Plans had been to deposit it at Port Gamble, but the sediment tested by the state Department of Ecology was too polluted to be deposited in open waters, so it will be transported to the nearby industrial park, he said.

It will be tested for pollutants at the Marine Drive site, and if it exceeds standards for uplands that are less stringent the those for open waters will be trucked to a dump site, likely the Roosevelt Regional Landfill in Eastern Washington, he said.

Hartman told commissioners at their regular Tuesday meeting that the cost of the dredging project could increase by about 50 percent if 20 percent of the fill must be trucked away, an estimate he said was conservative.

“It’s sad to see that project increased by 50 percent,” Commissioner Connie Beauvais said.

An estimate of 3,060 cubic yards of sediment could be transported to the landfill, a fifth of the 15,300 yards that will be dredged, Hartman said.

In a later interview, he further assessed the chance that material would have to be trucked off the site.

“The most likely scenario is that no material gets hauled off,” he said.

“We think a conservative planning scenario is that it’s all the way up to 20 percent.

“We want to make sure we’re prepared for this.”

The sediment was analyzed in core samples at the terminal, an export dock where private companies take on debarked logs.

Their skippers are concerned about touching bottom during low tide.

“If the berth is not dredged, bulk cargo vessels will stop taking cargo from Port Angeles,” Hartman predicted.

The sediment contains polychlorinated biphenyls (PCBs), dioxins, furans “and a whole host of metals,” Hartman said in an interview.

Hartman’s two reports on the dredging project are available at www.tinyurl.com/PDN-PortDredging.

Beauvais and port commissioners Steven Burke and Colleen McAleer authorized a contract amendment for the project and approved advertising for bids.

The amendment increases the amount the port is paying the Seattle-based Floyd-Snider consulting firm for construction oversite, analytical testing and production of a permitting outline and project schedule, by $115,000, to $422,000.

Commissioners advertised for bids without an estimate for the total cost of the project.

“That won’t be known until after the material has been dredged, stockpiled on-site and tested,” Hartman said in a report, adding it “may be well beyond the $1 million amount included in the 2020 capital budget.”

Dredging will begin in July and be “substantially complete” by Sept. 4, Hartman said.

Every 500 yards that are deposited at the industrial park will be tested for pollutants, Hartman said.

Harbor-floor depth at the terminal will be dug to 45 feet.

The material will be piled in the southeastern corner of the 18-acre Marine Drive site — where forester Grant Munro had his log yard — on the western edge of downtown Port Angeles and covered in plastic.

The material will be spread over a depressed area at the industrial park in 2021.

“The reason this site was the only solution was because the footprint of the dredging project is within an active cleanup site (Western Port Angeles Harbor) and significant liability would be tied to that material if placed on another property,” Hartman said in a report.

“Fortunately for the port, the KPly site was a previous cleanup site and so has the necessary monitoring wells and restrictive covenants already in place.”

The total amount that will be dredged also increased from 13,000 cubic yards, adding $80,000 to the contract.

Last dredged in 1978, Terminal 3 has seen little activity in recent months as logging activity has plummeted, port officials say.

________

Senior Staff Writer Paul Gottlieb can be reached at 360-452-2345, ext. 55650, or at pgottlieb@peninsuladailynews.com.

More in News

Paranormal investigator Amanda Paulson sits next to a photo of Hallie Illingworth at Lake Crescent, where Illingworth’s soap-like body was discovered in 1940. Paulson stars in a newly released documentary, “The Lady of the Lake,” that explores the history of Illingworth’s death and the possible paranormal presence that has remained since. (Ryan Grulich)
Documentary explores paranormal aspects disappearance

Director says it’s a ’ Ghost story for Christmas’

Funding for lodge in stopgap measure

Park official ‘touched by outpouring of support’

Joe Nole.
Jefferson County Sheriff Joe Nole resigns

Commissioners to be appoint replacement within 60 days

Residents of various manufactured home parks applaud the Sequim City Council’s decision on Dec. 9 to approve a new overlay that preserves manufactured home parks so that they cannot be redeveloped for other uses. (Matthew Nash/Olympic Peninsula News Group)
Sequim preserves overlay for homes

Plots can be sold, but use must be same

A ballot box in the Sequim Village Shopping Center at 651 W. Washington St. now holds two fire suppressant systems to prevent fires inside after incidents in October in Vancouver, Wash., and Portland, Ore. A second device was added by Clallam County staff to boxes countywide to safeguard ballots for all future elections. (Matthew Nash/Olympic Peninsula News Group)
Political party officials fine with Clallam’s loss of bellwether

With election certified, reps reflect on goals, security

For 20-plus years, Bob and Kelly Macaulay have decorated their boat and dock off East Sequim Bay Road for Christmas, seen here more than a mile away. However, the couple sold their boat earlier this year. (Doug Schwarz)
Couple retires Christmas boat display on Sequim Bay

Red decorations lit up area for 20-plus years

Hurricane Ridge day lodge funding held up in Congress

The fate of $80 million in funding to rebuild… Continue reading

Judy Davidson, left, and Kathy Thomas, both of Port Townsend, look over the skin care products offered by Shandi Motsi of Port Townsend, one of the 20 vendors at the second annual Procrastinators Craft Fair at the Palindrome/Eaglemount Cidery on Friday. (Steve Mullensky/for Peninsula Daily News)
Procrastinators Market

Judy Davidson, left, and Kathy Thomas, both of Port Townsend, look over… Continue reading

Services could be impacted by closure

Essential workers won’t get paid in shutdown

A now-deceased male cougar was confirmed by Panthera and Washington Department of Fish and Wildlife staff to have been infected with Avian influenza on the Olympic Peninsula. (Powell Jones/Panthera)
Two cougars infected with bird flu die

Risk of human infection still low, CDC says

D
Readers contribute $58K to Home Fund to date

Donations can be made for community grants this spring

Jefferson Elementary School in Port Angeles designated Thursday dress up like a candy cane day. Back row, from left to right, they are: Wyatt Farman, Ari Ownby, Tayo Murdach, Chloe Brabant, Peyton Underwood, Lola Dixon, River Stella (in wheelchair), Fenja Garling, Tegan Brabant, Odessa Glaude, Eastyn Schmeddinger-Schneder. Front row: Ellie Schneddinger-Schneder, Cypress Crear, Bryn Christiansen and Evelyn Shrout. (Dave Logan/for Peninsula Daily News)
Dress like a candy cane

Jefferson Elementary School in Port Angeles designated Thursday dress up like a… Continue reading