Port: Point Hudson jetty rebuild ahead of schedule

Earlier reopening likely, officials say

An aerial view of the north jetty shows it as it is being rebuilt at the Point Hudson Marina.

An aerial view of the north jetty shows it as it is being rebuilt at the Point Hudson Marina.

PORT TOWNSEND — The rebuild of the jetty at Point Hudson that protects the marina from storms is ahead of schedule, say officials with the Port of Port Townsend.

Capital Facilities Director Matt Klontz said last week that Orion Marine Contractors is a week or 10 days ahead of schedule and that the marina may be able to open earlier than Orion’s March 1 deadline, according to a press release.

Most of the 178 steel piles for the new jetty have been installed, including those that form the protective dogleg, Klontz said.

That means placing the new rock inside the pilings can start earlier than expected.

The marina has been closed since mid-September for the rebuild work. All boats were moved to the Boat Haven Marina or other locations. Only vessels waiting for work by Sea Marine at the head of Point Hudson are in the marina today.

“The placement of pilings has gone very well, without obstructions,” Klontz said, saying that it was due to Orion’s success in pulling out both old creosoted pilings and old stone above and below mud.

It turns out the old pilings weren’t as long as initially thought, he said.

Orion expected to remove a total of 480 tons of old pilings. The actual total was 250 tons.

Another surprise was the muted noise of the project to date, the result of Orion’s use of a vibratory hammer rather than a traditional pile-driver.

“Orion has been great to work with,” Klontz said.

Some of the new thick-walled steel pilings are 60 feet long, Klontz said. All were driven 25 to 30 feet below the mud line of Port Townsend Bay. All are 16 feet above the zero tide level.

The rebuild schedule also has benefited from mostly calm, sunny weather and the timely delivery of materials such as the steel piles.

Once the piles are all in place, the half-ton basalt stones that will fill the inside of the pilings will arrive by barge from Tacoma, the port said in the release.

The rock comes from a quarry near Orting. The huge overhead crane on site will load stones to the halfway point of the pilings, Klontz said in the release. Then tie rods will attach the pilings across the cribbing to one another. Afterwards, the rest of the rock will be loaded in with an excavator.

Orion is working on the north jetty now. The Tacoma-based firm is expected to return in September 2023 to rebuild the south jetty.

The entire project, which was in the works for at least a decade, is expected to cost $14 million, of which half comes from the U.S. Department of Commerce and another $2.5 million from Washington state.

The balance comes from the port’s voter-approved Industrial Development District levy, Jefferson County’s infrastructure fund and the U.S. Fish and Wildlife Service.

The current Point Hudson jetties were built in 1934. Deterioration over the decades has allowed windstorms to sweep through the marina during high winter tides. The marina has 50 boater slips, an annual 5,000 vessel visits and is home to business that employ more than 150 residents.

Matt Klontz, capital projects director for the Port of Port Townsend, surveys the new pilings now in place at the Point Hudson Marina.

Matt Klontz, capital projects director for the Port of Port Townsend, surveys the new pilings now in place at the Point Hudson Marina.

More in News

Hurricane Ridge day lodge funding held up in Congress

The fate of $80 million in funding to rebuild… Continue reading

Judy Davidson, left, and Kathy Thomas, both of Port Townsend, look over the skin care products offered by Shandi Motsi of Port Townsend, one of the 20 vendors at the second annual Procrastinators Craft Fair at the Palindrome/Eaglemount Cidery on Friday. (Steve Mullensky/for Peninsula Daily News)
Procrastinators Market

Judy Davidson, left, and Kathy Thomas, both of Port Townsend, look over… Continue reading

Services could be impacted by closure

Essential workers won’t get paid in shutdown

A now-deceased male cougar was confirmed by Panthera and Washington Department of Fish and Wildlife staff to have been infected with Avian influenza on the Olympic Peninsula. (Powell Jones/Panthera)
Two cougars infected with bird flu die

Risk of human infection still low, CDC says

D
Readers contribute $58K to Home Fund to date

Donations can be made for community grants this spring

Jefferson Elementary School in Port Angeles designated Thursday dress up like a candy cane day. Back row, from left to right, they are: Wyatt Farman, Ari Ownby, Tayo Murdach, Chloe Brabant, Peyton Underwood, Lola Dixon, River Stella (in wheelchair), Fenja Garling, Tegan Brabant, Odessa Glaude, Eastyn Schmeddinger-Schneder. Front row: Ellie Schneddinger-Schneder, Cypress Crear, Bryn Christiansen and Evelyn Shrout. (Dave Logan/for Peninsula Daily News)
Dress like a candy cane

Jefferson Elementary School in Port Angeles designated Thursday dress up like a… Continue reading

EYE ON THE PENINSULA: Jefferson commissioners to meet on Monday

Meetings across the North Olympic Peninsula

A 40-year-old Quilcene man died and a 7-year-old boy was airlifted to a Seattle hospital after the car in which they were riding collided with the back of a school bus on Center Road on Friday morning. (East Jefferson Fire Rescue)
One dies in two-vehicle collision involving school bus

A 40-year-old Quilcene man died and a 7-year-old boy was… Continue reading

Iris McNerney of from Port Townsend is like a pied piper at the Port Hudson Marina. When she shows up with a bag of wild bird seed, pigeons land and coo at her feet. McNerney has been feeding the pigeons for about a year and they know her car when she parks. Gulls have a habit of showing up too whenever a free meal is available. (Steve Mullensky/for Peninsula Daily News)
Feeding the birds

Iris McNerney of from Port Townsend is like a pied piper at… Continue reading

Property purchase intended for housing

Port Angeles envisions 18 to 40 residents

Housing, climate top Port Townsend’s state agenda

City also prioritizes transportation, support at Fort Worden

Dennis Bauer gets emotional while testifying at his triple murder trial in January 2022. His conviction was overturned by the state Court of Appeals and remanded back to Clallam County. (Paul Gottlieb/Peninsula Daily News)
Appeals court overturns murder conviction

Three-judge panel rules Bauer did not receive fair trial