Sediment, debris clog equipment at Elwha treatment plant

Silt-laden water is flushed into a side channel near the water intake for the industrial water treatment plant at the Elwha River west of Port Angeles Keith Thorpe/Peninsula Daily News

Silt-laden water is flushed into a side channel near the water intake for the industrial water treatment plant at the Elwha River west of Port Angeles Keith Thorpe/Peninsula Daily News

PORT ANGELES — Heavy loads of sediment and woody debris in a rain-swollen Elwha River are clogging filters and pumps at the Elwha Water Treatment Plant west of Port Angeles, Olympic National Park officials confirmed.

“Basically, they’re having to clean the filters a lot more frequently than anticipated,” park spokeswoman Barb Maynes said.

Drinking water is not being affected by the debris.

Port Angeles’ municipal water supply comes from a well near the river, not from the industrial water treatment plant that takes water straight from the river, Maynes said.

ADVERTISEMENT
0 seconds of 0 secondsVolume 0%
Press shift question mark to access a list of keyboard shortcuts
00:00
00:00
00:00
 

Water treated at the Elwha Water Treatment Plant, located 2.8 miles from the river mouth, goes to the Lower Elwha Klallam tribal fish hatchery, the state Department of Fish and Wildlife fish-rearing channel and the Nippon Paper Industries USA Inc. mill in Port Angeles.

Water leaving the treatment plant is well within standards, thanks to the efforts of crews, Maynes said.

“They’ve just been struggling keeping it maintained and on track,” Maynes said.

The Elwha Water Treatment Plant is operated by Veolia Water North America, one of several contractors involved in the National Park Service’s $325 million Elwha River restoration project that is keynoted by the removal of two dams.

A team of eight to 10 Park Service consultants and engineers was on site Monday and Tuesday making design modifications to the plant’s intake system.

“They’re trying to resolve it to get a permanent solution in place,” Maynes said.

The water treatment plant was designed to maintain fish-sustaining turbidity during removal of the Elwha and Glines Canyon dams.

Scientists have long known that removing the dams would trigger a large release of sediment that was stuck behind the dams in former lakes Aldwell and Mills for the better part of a century.

The anticipated sediment was the reason the treatment plant, fish hatchery and rearing channel were built in the first place.

“At this point, what I can tell you is that there have been some issues with the level of sediment and also organics — things like wood — working its way down the river,” Maynes said.

This debris caused a brief shutdown at the plant Sunday night. Workers have since been cleaning and monitoring filters, pumps and other equipment.

“It’s taking a lot more staff time and staff attention — and cleaning — to keep it operating,” Maynes said.

As of Tuesday, Maynes said there “haven’t been any problems” with the industrial water.

Nippon Paper Industries mill manager Harold Norlund was not immediately available for comment.

Maynes said the problem began “within the last week or so,” which coincides with a spike in river flows.

As river flows have ramped up, so have sediment and woody debris dislodged from the forest floor and reservoir beds.

Estimated river flows have soared from about 2,000 cubic feet per second last week to about 7,000 cfs over the weekend. The U.S. Geological Survey’s estimate for Tuesday afternoon was about 5,000 cfs.

Most of Glines Canyon Dam has been removed, allowing millions of cubic yards of silt, sand, cobble and gravel to flow over the top of what’s left of the former concrete high dam.

Elwha Dam was completely gone by March.

Dam-removal contractor Barnard Construction broke ground in September 2011 and expects to be finished with Glines Canyon Dam in May.

Maynes said it’s too soon to tell how fish are responding to the heavy sediment.

“Of course, it’s difficult to see them because the water is so muddy,” she said.

“There haven’t been very many collected at the hatchery. Lower numbers than last year are coming in, but that doesn’t mean they’re not out there.”

Reporter Rob Ollikainen can be reached at 360-452-2345, ext. 5072, or at rollikainen@peninsuladailynews.com.

More in News

From left to right, Northwest School of Wooden Boatbuilding students Krystol Pasecznyk and Scott McNair sand a Prothero Sloop with Sean Koomen, the school’s boat building program director. Koomen said the sanding would take one person a few days. He said the plan is to have 12 people sand it together, which will take a few hours. (Elijah Sussman/Peninsula Daily News)
Wooden boatbuilding school building ‘Twin Boats’

Students using traditional and cold-moulding construction techniques

Prevailing wage by trade across multiple counties in Washington state.
Prevailing wage s are driving up housing

Administrative burden may decrease competition

North Olympic Library System
Rendering of the new Sequim Library, which is currently under construction.
Library system board recognizes top donors

Naming opportunities still available

Port of Port Angeles approves roof rehab projects

McKinley Paper Company moves out of Marine Drive warehouse

Drug takeback day set across Peninsula on Saturday

Law enforcement agencies across the North Olympic Peninsula are poised to take… Continue reading

Public meeting set to meet administrator candidates

Jefferson County will host a public meeting at 5… Continue reading

Interfund loan to pay for Port Townsend meter replacement

City will repay over four years; work likely this winter

Artists to create murals for festival

Five pieces of art to be commissioned for downtown Port Angeles

Clallam assessor’s office to extend reduced hours

The Clallam County assessor’s office is continuing its reduction… Continue reading

Girders to be placed Thursday night

Contractor crews will place four 100-foot bridge girders over a… Continue reading

Cameras to check recycling contents in new program

Olympic Disposal will deploy a system of computerized cameras to… Continue reading

Port Angeles Fire Department responds to a residential structure fire on West 8th Street in Port Angeles. (Jay Cline)
Police: Woman arrested in arson investigation

Niece of displaced family allegedly said house was ‘possessed’