SEQUIM — A significant portion of the Sequim Community School remains in line for demolition.
But the overall plan for deconstruction of the aging and mostly unused school facility, along with a major overhaul of the district’s central kitchen, might get a significant overhaul.
The community got its first look at possible changes to the Sequim School District’s multi-mullion-dollar capital project last week at a series of community forums, where district staff presented three options for the project.
The public forums — ones that continue from 9 a.m. to 10:30 a.m. and 5 p.m. to 6:30 p.m. today and from noon to 1:30 p.m. Saturday, each at the district boardroom, 503 N. Sequim Ave. — aim to give input to the district’s five-member board when it considers next steps at a meeting slated for 6 p.m. Tuesday.
Sequim Schools Superintendent Gary Neal said proposals stem from conversations with Bernie O’Donnell, the northwest area development manager for Vanir Construction Management, Inc., who presented the options to the district in December after Vanir staff discovered some complexities with its original plan to deconstruct the Sequim Community School and renovate the district kitchen.
“The central kitchen is configured with sheer walls and broken up into narrow hallways, and it could make it difficult to put in some of the layout we had seen in other schools,” O’Donnell said. “It’s not the most efficient layout, but it doesn’t mean it can’t work.”
O’Donnell said some of these complexities include the current layout of the kitchen, servicing a loading and unloading dock at the kitchen’s site where trucks coming in and out to ship food to other parts of the district could pose a concern for student safety and replacing parts of an inverted roof.
“We looked at replacing some of this inverted roof; that would be costly, too,” O’Donnell said. “We got to this point where honestly we felt like, are we putting a band-aid on this?”
O’Donnell said Vanir felt it was in the best interest of the district to propose options that could maximize the district’s square footage to enable it to access more state matching funds once deconstruction is completed.
The three options — other than the original, or baseline, option — include renovating and moving the central kitchen to the northwest corner of the community school, so that if a new school is built on that site it is more efficient for long-term planning.
“We felt it was necessary for us to bring this to the community and to the district because we think there might be opportunities for some benefits,” O’Donnell said.
Neal said in the original planning phases when the capital project levy was made he did not know it had the capability of moving the kitchen to a different site of the community school.
“Vanir uncovered we don’t have to [renovate the kitchen] on that exact same spot,” Neal said.
“As long as we are within the footprint of where we have an existing space, we can put that kitchen wherever we want.”
Voters approved $5.75 million in funding for the capital projects levy in February 2017.
Pros, cons
Neal said all three options of moving and renovating the kitchen and deconstructing the remaining portions of the community school has been cleared by the state and allows the district to apply for $4.1 million in state matching funds.
Some options allow for more than $4.1 million in matching funds but one proposal (Option 1) puts the district over its budget at an estimated cost of $6 million.
The other impact in moving the kitchen and deconstructing the remaining portions of the community school could affect the spaces where Olympic Peninsula Academy (OPA) now holds classes for 100 students.
Options two and three could displace these students during the deconstruction process but Neal said the district could purchase portables to house Olympic Peninsula Academy students temporarily that are either on the same site as the community school or a different site within the district.
“Part of that contingency [in the budget] was that there were plans for OPA,” Neal said.
The benefit of these additional options, however, is that they could allow for better long-term planning if the district decides in the future it wants to use the space to build a new school, Neal said.
“If [the district] were to build a new school here … you’ve got the central kitchen right in the middle of the site,” O’Donnell said.
“Regardless if we get a new school or not, we know by deconstructing this it’s going to provide money for us down the road,” Neal said. “So at least we’re preparing for something in the future.”
Public input
At the forum, Nola Judd, who was a School Board candidate last fall, expressed concern that the district might put in a new school in the future that voters have said no to in the past.
“One of the things that concerns me is that we had several elections where the electorate said, no new school,” Judd said. “And we’re providing for the possibility of a new school we’ve already not got community support for? How are we going to propose we get that changed in their minds?”
Neal said the district will continue to ask the community for what it will support.
“I’m not saying we’re going to do that, but it is an opportunity,” Neal said. “We’re just saying we think it’s important the community knows we have a vision and here’s our vision.”
Neal said if a new school does not get put in in the future, the district might have to look to buying portables to house more students.
Baseline
This option maintains the district’s original objective of deconstructing the Sequim Community School and renovating the central kitchen in its current location. This option will cost about $3.85 million with $1.89 million remaining.
Pros: This plan is within the district’s budget and still qualifies for state matching funds of $4.1 million for new construction and is what was advertised to voters when they passed the Capital Projects Levy.
Cons: The kitchen operations will need to be relocated during renovation and Olympic Peninsula Academy (OPA) may be impacted but manageable. There will be constraints to an efficient layout of the renovated kitchen due to the existing structural walls and space limitations. The loading and unloading operations of trucks is located in the center of the site and is not the best safety option.
Note: The district does not consider this option the best long-term solution for school operations.
Option 1
This option moves the central kitchen to the northwest corner of the Sequim Community School with deconstructing the community school. This option would cost about $6 million with a negative balance of $307,000.
Pros: Deconstructing the existing kitchen and OPA spaces will allow more square footage to be counted for state matching funds, about $4.1 million plus $1.25 million. Kitchen operations will remain in the same place until the new kitchen is constructed. The new kitchen will be 100 percent code compliant and all new systems for lowest long term maintenance impacts. The loading and unloading operations of trucks can be separated from school operations for safety.
Cons: This option puts the district over budget and it would have to dip into its reserve funds. OPA will need to be relocated.
Note: The district does consider this one of the best long-term solutions for school operations.
Option 2
This option would renovate the west wing for OPA classes and an efficient layout kitchen in optimal location of site with deconstructing the remaining portion of the community school. This would cost $5.68 million with a positive balance of $62,000.
Pros: $4.1 million in state matching funds are available plus an additional $500,000 to be counted towards square footage. Kitchen operations will not need to be relocated and will move when new kitchen is ready. OPA spaces would remain until new future school is constructed. New kitchen 100 percent code compliant and is efficient for layout and staff operations. Location of kitchen is optimized for new school construction. Loading and unloading operations of trucks separated from school operations for safety.
Cons: The district does not consider this the best long-term solution for school operations because it only partially maximizes state matching funds, and the space renovated for OPA may not be compatible with long-term new school on site.
Option 3
This option renovates the west wing for an efficient-layout kitchen in optimal location of site with deconstructing the remaining portion of the community school and OPA would need to relocate off site. It would cost $5.36 million in budget with a positive balance of $383,000.
Pros: $4.1 million in matching funds plus additional $1 million for deconstructing existing kitchen and OPA space for more square footage. Kitchen operations will not be impacted and will move when new kitchen is ready. New kitchen will be 100 percent code compliant and all new systems for lowest long term maintenance. It will allow for efficient layout and equipment for kitchen staff operations and future school. Loading and unloading of trucks can be separated from school operations for safety.
Cons: OPA will need to relocate but it is within the district’s budget to do so.
Note: The district considers this option one of the best long-term solutions for school operations and achieves the district’s original objective.
________
Erin Hawkins is a reporter with the Olympic Peninsula News Group, which is composed of Sound Publishing newspapers Peninsula Daily News, Sequim Gazette and Forks Forum. Reach her at ehawkins@sequimgazette.com.