State ferries system ‘sets record straight’ on Chetzemoka

Washington State Ferries last week released a document to “set the record straight” on the new MV Chetzemoka ferry, which serves the route between Port Townsend and Whidbey Island.

It was released to address rumors and “a few inaccuracies in various media reports” (none of which was carried in the Peninsula Daily News):

Ferry’s tilt

Inaccuracy: The Chetzemoka has an unanticipated or unintended incline to one side (list) that is noticeable while the boat is sailing, making it inefficient and creating safety concerns.

Correct information: The 1 percent list is part of the design to maximize the number of trucks/oversize vehicles the vessel can carry and is due to the location of three stair towers and two elevators on one side.

Based on the design, the ferry has no list when loaded with vehicles. As part of the vessel’s certification process, the Coast Guard performed a vessel-wide stability test and deemed the Chetzemoka safe.

The Island Home, a Massachusetts ferry whose design was used for the Chetzemoka, also has a designed-in 1 percent list that is eliminated when the vessel is loaded with vehicles.

There is no plan to add ballast (weight) to counter this list when the vessel is not loaded.

Expense

Inaccuracy: The Chetzemoka is the most expensive ferry ever built in the United States.

Correct information: WSF’s Jumbo Mark II ferries cost $86 million each. The Kennicott (Alaska) cost more than $80 million.

The Superferries Alakai and Huakai, built for Hawaiian waters, came in at $85 million and $91 million, respectively.

(Note: The Chetzemoka is the most expensive ferry built by the state of Washington. It is also the first the state has built in more than a decade.)

Cost overrun

Inaccuracy: The Chetzemoka was supposed to cost $65.5 million but instead cost $80.1 million.

Correct information: The final cost of the Chetzemoka was $79.4 million.

The original budget was $76.93 million, including construction, risk and contingency, and construction management.

The $65.5 million figure was the construction bid from Todd Shipyards. It is standard practice in capital budgeting to include contingency and risk costs and construction management.

There has been an additional $663,000 of work on the Chetzemoka that will be charged to the three-vessel procurement program.

When the state Legislature funded the second and third vessels with a $136.3 million budget, WSF combined that with the $76.93 million Chetzemoka budget, giving one budget for all three boats totaling $213.2 million.

Original estimate

Inaccuracy: The original engineer’s estimate to build the Chetzemoka was $49.5 million.

Correct information: The original $49.5 million engineer’s estimate was calculated assuming there would be competition.

At the start of the process, four shipyards were interested. Three removed themselves for various reasons, including bonding and apprenticeship goals.

A $58.2 million engineer’s estimate was used at bid opening, using the labor rate of the single source bid.

The final construction bid was $65.5 million, or an 11 percent difference from the engineer’s estimate.

Plaguing problems?

Inaccuracy: WSF crews say the Chetzemoka is plagued with problems.

Correct information: The captains and crews who have trained on and are operating the Chetzemoka are pleased with the vessel’s performance.

A number of media outlets have interviewed the captains and crews of the vessel, who are very forthright in their approval of the vessel.

Propellers inefficient?

Inaccuracy: The Chetzemoka’s propellers are inefficient.

Correct information: The Island Home (a Massachusetts ferry whose design was used for the Chetzemoka) has fixed-pitch propellers like the Chetzemoka that operate well in challenging waterways with currents and restricted harbors in Massachusetts.

WSF developed procedures and engine-control protocols during several weeks of sea trials to ensure efficient operation.

The vessel is operating on WSF’s most challenging route, with strong crosscurrents at the narrow, shallow Keystone Harbor (on Whidbey Island).

Design, build ferries?

Inaccuracy: WSF needs to get out of the business of designing and building vessels.

Correct information: WSF does not design or build vessels.

Elliott Bay Design Group designed the Chetzemoka, and Todd Pacific Shipyards built it.

More in News

Lost Mountain Station 36 at 40 Texas Valley Road recently sold to a neighbor after Clallam County Fire District 3 was unable to recruit volunteers to staff the station. Its proceeds will go toward future construction of a new Carlsborg Station 33. (Matthew Nash/Olympic Peninsula News Group file)
District sells one fire station

Commissioners approve 2025 budget

Clallam County Master Gardener Gordon Clark cuts leaves off Isobel Johnston’s agave plant that she had been growing for 28-plus years. She specifically requested Master Gardeners help her remove the plant while keeping at least one for years to come. (Matthew Nash/Olympic Peninsula News Group)
Master Gardeners help remove agave plant on Fifth Avenue

Several baby plants uncovered below large leaves

Harvey Hochstetter tosses a box of food to Cameron Needham to stack with fellow volunteers like Bill Needham, right, for the Sequim Food Bank’s Holiday Meal Bag Distribution event. Cameron, his father Ty and grandfather Bill were three generations helping the program. (Matthew Nash/Olympic Peninsula News Group)
Sequim Thanksgiving program helps 1,200 families

About 30 volunteers pack holiday boxes

Security exercise set at Indian Island

Naval Magazine Indian Island will conduct a security training… Continue reading

Operations scheduled at Bentinck range this week

Training at the land-based demolition range on Bentinck Island… Continue reading

Weekly flight operations scheduled

There will be field carrier landing practice operations for aircraft… Continue reading

Janet Lucas, left, finds a special purchase of a “mail manager” at Swains early Friday morning. Black Friday shoppers descended on the Port Angeles store at 8 a.m. There were dozens of early risers who went looking for special bargains on one of the biggest shopping days of the year. (Dave Logan/for Peninsula Daily News)
Black Friday

Janet Lucas, left, finds a special purchase of a “mail manager” at… Continue reading

Clallam adopts housing needs

Population projected at 86,700 by 2045

The Wall That Heals, a Vietnam War memorial, coming to Port Townsend

Opening ceremony to be held at Jefferson County airport on Sept. 11

Sherry Phillips, chair of the Festival of Trees design committee, stands next to the tree Twelve Days of Christmas, which she designed personally. (Leah Leach/for Peninsula Daily News)
Port Angeles woman shares joy of decorating trees

Sherry Phillips lends talent for all of festival’s 34 years

EYE ON THE PENINSULA: Public hearings set on proposed 2025 budgets

Meetings across the North Olympic Peninsula

Serving up a Thanksgiving meal are, from left, Taylor Hale, Gina Landon, Shawn Lammers, Ryan Lammers, Sara Taylor and Jean Ball, all volunteers with Holiday Meals, located in the Tri-Area neighborhoods of Chimacum, Port Hadlock and Irondale. The group expected to serve up to 460 full Thanksgiving dinners with 287 being picked up, 118 delivered and 55 eaten at the Tri-Area Community Center. (Steve Mullensky/for Peninsula Daily News)
Thanksgiving meals kick off holiday joy

Smiles, warmth light up Queen of Angels Catholic Church