SEQUIM — The name bears no glamour, but community groups clamor for a piece of it: Sequim’s Water Reuse Demonstration Site, a nearly 28-acre swath north of Carrie Blake Park at 202 N. Blake Ave., is a object of desire for Sequim Family Advocates, a grass-roots group of parents who want playfields added; for the Clallam County Master Gardeners, who want to build a classroom beside their demonstration garden; and the Sequim City Band, which hopes for a 500-seat auditorium added onto the James Center band shell.

And though the Sequim City Council has expressed support for all three ideas, the state Department of Ecology has the final say on whether any will become reality.

On Monday night, Sequim Capital Projects Manager Frank Needham sought to explain all of this to the Sequim City Council — and to Sequim’s new public works director, Ben Rankin. He’s just arrived from Clemson, S.C., where he was the city engineer. Sequim Interim City Manager Linda Herzog hired him in May; on Monday she told the council he’s here to listen, learn and potentially reprioritize his department’s project list in the coming weeks.

The water reuse site, Needham began, is property the city has developed since the mid-1990s with millions in grants from the Department of Ecology.

“The intent was to demonstrate how we could use reclaimed water in a very public way,” so a fishing and model-boating pond, restrooms and stretches of lawn were put in, all with water from the city’s state-funded reclamation plant. Today, the plant produces an average 600,000 gallons of reclaimed water each day, Needham said.

That water can be used for the Master Gardeners’ demo garden, but the proposed classroom building presents problems. Needham said it will bring “impervious surfaces,” concrete or asphalt that contribute to stormwater runoff, a major factor in the pollution of local streams and the Strait of Juan de Fuca.

The gardeners will have to come forward with “creative solutions,” Needham added, such as putting a green roof — a roof rife with native plants — on the classroom or choosing a building-pad surface that absorbs water before it runs off.

Sequim Family Advocates, a group led by soccer dads Dave Shreffler and Craig Stevenson, has told the council it will raise the money to build playfields at the water reuse site. The city will provide reclaimed water for the fields, Needham said, but the state Department of Health will require that it be chlorinated.

The proposed auditorium at the James Center presents a more complex problem. Ecology officials told Herzog that a 500-seat concert hall, even with added restrooms where reclaimed water would be used, isn’t at all what the state had in mind.

Needham provided some history: After the reuse site was established, then-public works director James Bay was the one who persuaded Ecology to allow a band shell to be built; state officials “thought it was going to be teaching seminars” on water reuse.

In fact, the building, named the James Center, after Bay, is a venue for free concerts throughout the summer. Patsy Mattingley of the Sequim City Band has led a campaign to expand it to include an indoor space, touting the benefits a performing arts center would bring to Sequim.

Herzog, hoping to salvage the expansion idea, suggested a land swap. If Sequim could find a 5-acre parcel elsewhere in town to demonstrate water reuse, she asked, would Ecology allow construction of the concert hall on the original water reuse site?

Needham said it’s still not clear, however, whether Ecology and Sequim can make that idea work; the state could still prohibit the concert hall on the reuse site, forcing Mattingley and her project team to look for another location.

The city must next confer with Mattingley, Needham said, on whether the team wants to move forward with its original plan, move off the water reuse site or scrap the concert hall altogether.

“Let’s hope they go forward,” he said finally. “It’s a great project.”

Sequim-Dungeness Valley reporter Diane Urbani de la Paz can be reached at 360-681-2391 or at diane.urbani@peninsuladailynews.com.

More in News

Oliver Pochert, left, and daughter Leina, 9, listen as Americorp volunteer and docent Hillary Sanders talks about the urchins, crabs and sea stars living in the touch tank in front of her at the Port Townsend Marine Science Center. Pochert, who lives in Sequim, drove to Port Townsend on Sunday to visit the aquarium because the aquarium is closing its location this month after 42 years of operation. (Steve Mullensky/for Peninsula Daily News)
Aquarium closing

Oliver Pochert, left, and daughter Leina, 9, listen as Americorp volunteer and… Continue reading

Tree sale is approved for auction

Appeals filed for two Elwha watershed parcels

Port Townsend City Council to draw down funds in 2025 budget

City has ‘healthy fund reserve balance,’ finance director says

Man flown to hospital after crash investigated for DUI

A 41-year-old man was flown to Olympic Medical Center in… Continue reading

Signal controller project to impact traffic

Work crews will continue with the city of Port… Continue reading

Cities, counties approve tax hikes

State law allows annual 1 percent increase

Health officer: Respiratory illnesses low on Peninsula

Berry says cases are beginning to rise regionally

A puppy named Captain Kirk is getting ready for adoption by Welfare for Animals Guild after it was rescued near Kirk Road. An unsecured makeshift kennel fell out of a truck on U.S. Highway 101 last month and was struck by another vehicle. (Welfare for Animals Guild)
Puppy rescued from wreck to be adopted

A puppy named Captain Kirk is about to boldly go… Continue reading

Festival of Trees raises record $231,000

The 34th annual Festival of Trees, produced by the… Continue reading

Man flown to hospital after single-car collision

A 67-year-old man was flown to an Everett hospital after… Continue reading

Lost Mountain Station 36 at 40 Texas Valley Road recently sold to a neighbor after Clallam County Fire District 3 was unable to recruit volunteers to staff the station. Its proceeds will go toward future construction of a new Carlsborg Station 33. (Matthew Nash/Olympic Peninsula News Group file)
District sells one fire station

Commissioners approve 2025 budget