Construction crews work to rebuild the Rialto Beach jetty as seen from across the Quillayute River from LaPush. (Lonnie Archibald)

Construction crews work to rebuild the Rialto Beach jetty as seen from across the Quillayute River from LaPush. (Lonnie Archibald)

Work underway on damaged section of Rialto revetment at La Push

U.S. Army Corps of Engineers estimates that the repairs on the 300-foot-long section of the protective jetty will be finished in about three weeks.

LA PUSH — Work continues on a 300-foot-long damaged section of the Rialto revetment near La Push, with the U.S. Army Corps of Engineers estimating repairs will be completed in about three weeks.

Coastal revetments are sloping structures placed on banks or cliffs that absorb the energy of incoming water in order to prevent erosion. The damaged barrier is essentially a rocky jetty that protects La Push.

A 300-foot-long stretch of the revetment has failed on the west side, according to the Corps, and only the underlying gravel berm remains.

ADVERTISEMENT
0 seconds of 0 secondsVolume 0%
Press shift question mark to access a list of keyboard shortcuts
00:00
00:00
00:00
 

So far, the project is slated to cost about $1.6 million, said Patricia C. Graesser, U.S. Army Corps of Engineers public affairs supervisor for the Greater Seattle area.

The repairs are being conducted by Bruch & Bruch Construction Inc. of Port Angeles, Columbia Granite LLC of Olympia, and SEA Construction LLC of Raymond.

“A crew of three from the Corps is overseeing repairs to the revetment and expect to complete work in the next few weeks,” Graesser said.

It isn’t clear exactly when or how the revetment was damaged, but officials believe winter storms last year were likely the cause, said Bill Dowell, U.S. Army Corp of Engineers spokesperson.

Noticed in spring

The damage was first noticed in late March or early April of this year, he said.

Before construction crews and heavy equipment could access the revetment, a damaged stretch of Mora Road in Olympic National Park — the only access road to the site — needed to be repaired and widened, Graesser said.

A Corps team began widening the road Oct. 14 to allow trucks to haul material to the revetment for the needed repairs.

As of Friday, contractors were delivering stone to the site that will be used to strengthen the barrier, Graesser said.

The 3,000-foot-long revetment was built in 1974 and last rehabilitated after a breach in 1996, Graesser said.

The structure’s crest in the damaged area is between four and six feet lower than the design elevation and adjacent structure elevation, according to the Corps. Given the revetment’s condition, if no action was taken a breach in the damaged area would be highly probable.

Emergency repair efforts were prompted by a series of storms that arrived in the Pacific Northwest beginning Oct. 13, according to Graesser.

If the revetment had been breached during the storms, it could have exposed the Quileute reservation riverward shoreline, Coast Guard Station, training wall and Quileute Marina to direct wave action, Graesser said.

A training wall is an artificial embankment or wall for directing the course of a stream or river, in this case the Quillayute River, which runs to the east of Rialto Beach.

The training wall is not designed to protect the marina or other facilities from wave action and likely would have been destroyed if exposed to ocean waves and debris, Graesser said.

Because the marina is the only safe harbor for 60 miles along the Pacific Ocean, the Corps initiated emergency repairs to the revetment, Graesser said.

“Because of the threat of a breach, we received emergency funding to address the immediate threat,” she said.

“Additional work will still be required after storm season.”

The threat underscores efforts by the Quileute tribe to move much of its community. Much of the reservation — including the existing school site adjacent to First Beach, the Quileute Tribal Center, the Quileute Senior Center and many homes — is directly in the path of possible tsunamis or flooding from the Quillayute River, according to the Quileute tribe.

________

Features Editor Chris McDaniel can be reached at 360-452-2345, ext. 56650, or at cmcdaniel@peninsuladailynews.com.

Reporter Jesse Major contributed to this report.

Road closed signs are set up at the Mora Ranger Station on the Mora Road as the road from that point on to Rialto Beach is closed due to work being done on the rialto Beach jetty. (Lonnie Archibald)

Road closed signs are set up at the Mora Ranger Station on the Mora Road as the road from that point on to Rialto Beach is closed due to work being done on the rialto Beach jetty. (Lonnie Archibald)

More in News

Supreme Court says no to recall reconsider

Sequim man found liable for legal fees

Chimacum Ridge seeks board members

Members to write policy, balance values, chair says

Fire destroys shop east of Port Angeles

A fire on Hickory Street east of Port Angeles… Continue reading

Jefferson Transit Authority to expand Kingston Express route

Jefferson Transit Authority has announced expanded service on its… Continue reading

From left to right, Northwest School of Wooden Boatbuilding students Krystol Pasecznyk and Scott McNair sand a Prothero Sloop with Sean Koomen, the school’s boat building program director. Koomen said the sanding would take one person a few days. He said the plan is to have 12 people sand it together, which will take a few hours. (Elijah Sussman/Peninsula Daily News)
Wooden boatbuilding school building ‘Twin Boats’

Students using traditional and cold-moulding construction techniques

Prevailing wage by trade across multiple counties in Washington state.
Prevailing wages are driving up housing

Administrative burden may decrease competition

North Olympic Library System
Rendering of the new Sequim Library, which is currently under construction.
Library system board recognizes top donors

Naming opportunities still available

Port of Port Angeles approves roof rehab projects

McKinley Paper Company moves out of Marine Drive warehouse

Drug takeback day set across Peninsula on Saturday

Law enforcement agencies across the North Olympic Peninsula are poised to take… Continue reading

Public meeting set to meet administrator candidates

Jefferson County will host a public meeting at 5… Continue reading

Interfund loan to pay for Port Townsend meter replacement

City will repay over four years; work likely this winter

Artists to create murals for festival

Five pieces of art to be commissioned for downtown Port Angeles